Title Page
-
Site conducted
-
Inspection Date
-
Pour Date
-
Lot Number
-
Pour Description
-
Correct Setout of Concrete Deck & Stairs as per Latest IFC Drawings.
-
Install Formwork and Falsework. Formwork & Falsework to be Clean & Free of Organic Matter
-
Prep & Place Correct Reo to Concrete Deck as per Latest IFC Drawings - Bottom Layer N12 at 150mm Centres each way. Top Layer N12 at 150mm Centres each way. 45mm Top Cover & 45mm Bottom Cover
-
Prep & Place Correct Reo to Concrete Deck Penetration as per Detail 6 on IFC Drawings (300mm x 300mm) - 2-N12 Trimmer Bars each side with 300mm lap length.
-
Prep & Place Correct Stair Reo as per Latest IFC Drawings - One Layer N12 Bars Vertical & Horizontal at 200mm Centres.
-
Prep & Place Starter Bars for Pump Plinth as per Latest IFC Drawings - N12 Starter Bars at 150mm Centres with 300mm Lap Length in Bottom Layer of Concrete Deck Reo.
-
Prep & Place 2 Rows of M16 Ancon Qwikfoot Threaded Inserts at 150mm Spacings to suit Inline Thrust Block as per IFC Drawings
-
Order Correct Strength of Concrete - Strength?
-
Concrete Strength N40 or above?
-
Concrete Slump
-
Concrete Qty
-
Pump Required
-
Water Added
-
How much?
-
HOLD POINT - PRE-POUR INSPECTION by STP Consultants
-
Inspector Name & Signature
-
Pour Concrete Deck & Footings
-
Vibrate all Concrete
-
Apply Aliphatic Alcohol to Concrete after Bull Floating
-
Machine Trowel Finish Concrete
-
Apply Curing Agent
-
Strip Formwork & Clean
-
Complete Concrete Pour Record Sheet
-
Take Photos of Concrete Dockets
ITP Sign OFF
-
ITP Sign Off - FERGUS BUILDERS
-
ITP Sign Off - STP CONSULTANTS