Title Page
-
Site conducted
-
Inspection Date
-
Lot Number
-
Description
-
Ground Environments Piling Platform Design
-
Survey setout of piling rig platform by RPS Surveys
-
Box out piling rig platform to required depth
-
Compact sub grade with 12 tonne roller
-
Survey setout of pile locations by RPS Surveys
-
Install 1st Layer of Geogrid TX160 & cut holes in pile locations
-
Import & compact 300mm layer of crushed concrete 30-100mm
-
Inspection by Ground Environments Engineer
-
Take photo of Inspection Record
-
Survey setout of pile locations by RPS Surveys
-
Install 2nd Layer of Geogrid TX160 & cut holes in pile locations
-
Import & Compact 2.3 road base to total depth of 400mm
-
Inspection by Ground Environments Engineer
-
Take photo of Inspection Record
-
Compaction tests undertaken by Soil Engineering Services and passed
-
ITP Sign Off - FERGUS BUILDERS
-
ITP Sign Off - GROUND ENVIRONMENTS
-
Take photo of Form 15 or Inspection Record