Title Page
-
Site conducted
-
PM Number
-
Notification Number (If multiple Notification numbers separate them by a comma.)
-
Conducted on
-
Inspector Name
-
Inspector LanID
-
Following the Lone Worker Requirements, do you have your device (i.e. Beacon or similar device) with you at all times and turned on?
-
Why don't you have one?
- I have never been issued one.
- I lost it.
- The battery doesn't hold a charge.
- It has been stolen. (i.e. Truck broken into.)
- Other - Add comments below.
-
Division
-
Group Location
-
MAT
-
Contractor Name (include subcontractor name if applicable)
-
Crew Foreman's name (First & Last)
-
Crew Size
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
-
Was there a Safety Professional present on the job site? (If so add their name/s)
-
What equipment was on-site?
-
Work Location
-
Job Scope
-
Circuit/Voltage
-
AFW Type and Switch log number
-
Was job found completed on arrival? (If so mark all questions N/A on the next page.)
-
Was the job cancelled?
-
Reason for cancellation?
Daily Fire Mitigation Actions
-
Preventing and Mitigating Fires While Performing PG&E Work
-
What is the Utility Fire Potential Index (FPI) Rating today?
- "R1": Very little or no fire danger.
- "R2": Moderate fire danger.
- "R3": Fire danger is so high that care must be taken using fire-starting equipment. Local conditions may limit the use of machinery and equipment to certain hours of the day.
- "R4": Fire danger is critical. Using equipment and open flames is limited to specific areas and times.
- "R5": Fire danger is so critical that the use of some equipment and open flames is not permitted.
- "R5-Plus": The greatest level of fire danger where rapidly moving, catastrophic wildfires are possible. Typically, this is when fire danger is extreme; “plus,” there are high-risk weather triggers (e.g., strong winds). PSPS triggering event is an example.
-
What level of fire mitigation was required today? (Select all that apply
- Jobsite has enough tools to outfit all crew members at the operation.
- 5-gallon backpack pump-type fire extinguisher
- A trailer-mounted water tank, water tender, or other water-delivery/fire-suppression.
-
If a Fire Watch is required, what was their name?
General Safety
-
1.0 Did you attend crew tailboard?
-
1.1 Was all required PPE used?
-
1.2 Were all Covid protocols followed? Mask, social distancing, visitor log etc
-
1.3 Was PSP (Programmatic Safety Plan) or PSSP (Project Site Safety Plan) on site?
-
1.4 Were adequate fire mitigation measures in place (per TD1464S)
-
1.5 Were safe worksite practices used including use of spotters, wheel chocks, parking brakes, outriggers, booms/buckets/forks lowered when parked or stored
-
1.6 M&TE (Material & Test Equipment) that is to be used for a job has been checked for calibration compliance; Equipment dielectric certification valid.
-
1.7 Was traffic control needed?
-
1.7a Was traffic control safe and effective?
-
1.7b Even though not needed was Traffic Control present?
-
1.8 Were there any issues with material availability?
-
1.9 Was any equipment leaking?
-
Was environmental contacted?
-
Was equipment returned to contractor yard or PGE facility?
-
1.10 Was a crane required?
-
1.10a Were all certifications in place?
-
1.11 If a helicopter was used, was a preflight tailboard with the pilot and crew conducted
-
1.12 Was Vegetation clearing needed (4' minimum clearance) and completed?
-
1.12a Was a tag created if necessary?
-
1.13 Is your work site in a forest, brush or grass covered land?
-
1.14 Is your work site an R4 or above?
-
1.15 Has the water buffalo been tested and is ready for service?
-
1.16 Have all potential fire hazards been mitigated?
-
1.16 Have all potential fire hazards been mitigated? Comment here.
-
1.17 Is there a valid dig ticket (USA) for this location/s? (Add photo of markings on the ground.)
Electric
-
3.0 Were Rubber Gloves air and water tested prior to use?
-
3.1 Were all second points of contact covered?
-
3.2 Are conductive objects hanging on the outside of the Bucket?
-
3.3 Was required fall protection in place?
-
3.4 Was voltage detector tested prior to use?
-
3.5 Was Customer Voltage verified prior to and after work was completed by you?<br>(Example: Check Voltage/Rotation after Transformer replacement at meter<br>panel) (Refer to attached document)<br>
-
3.6 Was the equipment voltage (Name Plate) verified by you? If not, why?
-
Examples of Name Plate pictures
-
5MM_Neutral_ID_Voltage_Testing (003)
-
Voltage and Phase Rotation Check on Secondary Connections
Job Completion
-
4.0 Did outage start on time?
-
Why?
-
4.1 Did outage end on time?
-
Why?
-
4.2 Was all work completed as planned (ready for closeout) or in progress over multiple days?
-
4.3 Blank (Question related to Cancellation moved to Title Page)
-
4.4 Did you encounter issues during planning or execution of the job?
-
Include recommendations to prevent recurrence
-
4.5 Was the job built to PGE safety, quality, and compliance standards?
-
Describe any issues
-
4.6 Attach minimum 3 photos of each location (Bottom Half, Top Half, Whole Pole/Location) of completed work.
-
4.7 Please use this area to add any notes and corresponding photos concerning this job that you deem appropriate. (Add notes concerning Red Line Approvals in this area also)
-
4.8 How many questions were marked Red?
- 0
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
-
Inspectors Signature