Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location
  • PM #

  • Location #

  • Foreman

Enclosure

  • Enclosures?

  • (Grey Item) Encl. / Lid secured (bolted, no public hazard) GO 128: Rule 32.7

  • (Grey Item) Set at grade and level with no tripping hazard ( Enclosures 062000 Rev.24: Pg. 1 Note 7, Pg. 25 Step 2)

  • (Grey Item) HV sign/Ownership, Equip. # on lid as required (Enclosures 062000 Rev.24: Pg. 2 Note 14)

  • Minimum clearances to walls, overhangs, etc. (General 051122 Rev.21: Pgs. 2-7)

  • Enclosure correctly sized (Enclosures 062000 Rev.24: Pg. 4 Table 1)

  • Correct traffic lid installed (Enclosures 062000 Rev.24: Pg. 6 Table 2)

  • Working Space: clearance maintained as required (General 051122 Rev.21: Pgs. 4-6)

  • Retaining wall installed as required (General 051122 Rev.21: Pgs. 5, 7-9)

Pad-Mounted Equipment

  • Pad-mounted equipment?

  • (Grey Item) Securely anchored per standard (Transformers 045291 Rev.12: Pg. 3 Items 1-2 & 29 Various Figures; Switches 053318 Rev.21: Pg. 4 Detail A, Pg. 9, Figure 5 Table 6 Item 2)

  • (Grey Item) Caulking applied, no gaps into compartments (Transformers 045291 Rev.12: Pg. 1 Note 11)

  • (Grey Item) Windows grouted (Transformers 045292 Rev.13: Pg. 2 Note 17)

  • (Grey Item) High-Voltage / Maintain 8' Clearance label on exterior door as required (Marking 033582 Rev.07: Pg. 1 Note 4)

  • (Grey Item) Equip. # installed on interior/exterior of equip. (Marking 033582 Rev.07: Pgs. 3-4, Pg. 10 Note 2)

  • (Grey Item) Security: Exterior door bolted and locked. (Transformers 045291 Rev.12: Pg. 3 Item 15 various figures)

  • (Grey Item) Working Space: 8’ clearance in front of doors (General 051122 Rev.21: Pg. 4 Note 4-B-a)

  • (Grey Item) Barrier posts installed as req’d (vis. strips, locked) (General 051122 Rev.21: Pgs. 10-27).

  • Pad is level (Transformers 045292 Rev.13: Pg. 1 Note 9)

  • Minimum clearances to walls, overhangs, etc. (General 051122 Rev.21: Pgs. 2-3)

  • Retaining wall installed, as required (General 051122 Rev.21: Pgs. 5-9)

Live-Front Equipment

  • Live-front equipment?

  • (Grey Item) High-Voltage barricade installed, signed, and locked (Transformers 042761 Rev.09: Pg. 1 Note 6; Transformers 045290 Rev.22: Pg. 1 Note 7)

  • (Grey Item) Stress cone tape not split or damaged (GO 128: Rule 17.1)

  • Hot taps 2" or more from barricade surface (Transformers 045290 Rev.22: Pg. 4 Note 3)

Subsurface Equipment

  • Subsurface equipment?

  • (Grey Item) Operating number installed inside enclosure (Marking 033582 Rev.07: Pg. 3 Note 8, Pg. 4, Note 10).

  • Switches securely anchored to enclosure (Switches 050859 Rev.18: Pg. 5 Note 6; Switches 054686 Rev.13: Pg. 2 Note 20)

Workmanship

  • Workmanship?

  • (Grey Item) Verify job site is clean and excess material is picked up (GO-128 Rule 17.1)

Grounding

  • Grounding?

  • (Grey Item) HO/Ground Buss/Ring Buss/Ground source sized and installed correctly (General 060462 Rev.14).

  • (Grey Item) Pad-mount exterior ground rod not exposed (General 060462 Rev.14: Pg. 1 Note 8, Pg. 3 Sect. A-A)

  • Ground connections installed per standard (type, surface cleaned, correct dies, & # of crimps) (General 060462 Rev.14)

  • Enclosure and frame grounded per standard (General 060462 Rev.14: Pg. 1 Note 5, Pg. 5 Figure 2; TD-060462B-001 & TD-060462B-002)

  • Neutral bypass on primary splices installed correctly (Terminations 051071 Rev.11: Pg. 18 Table 20)

  • Concentrics pressed to ring buss/grid (General 060462 Rev.14: Pgs. 3-4 & 6-7, Pg. 3 Note 4)

  • Ground rods installed per standard (One - 3/4" x 12' subsurface; 2 - 5/8" x 8' Pad Mount) (General 060462 Rev.14: Pg. 1 Note 4 & 7, Pg. 2 Items12-13)

  • TX neutral spade connected to the ground grid when serving grounded services (General 060462 Rev.14: Pg. 2 Note 12)

  • TX Neutral spade insulated (ungrounded services) (General 060462 Rev.14: Pg. 2 Note 13)

Cables/Conduits

  • Cables/conduits?

  • (Grey Item) Voltage tags installed on primary cables (Marking 033582 Rev.07: Pg. 1 Notes 2 & 5, Pg. 2 Note 5-B)

  • Cables & splices adequately supported with correct bending radius (Primary & Secondary) (Transformers 060578 Rev.15: Pg. 3 Item 20, Pg. 4 Figure1; Cable 028077 Rev.05; Cable 038193 Rev.14: Pg. 4 Note 11, Table 1; Transformers 045291 Rev.12: Pg. 1 Note 5, Pg.11 Detail E)

  • Phase / sectionalizing tags installed on primary cable (Marking 033582 Rev.07: Pg. 1 Notes 1-2 & 5, Pg. 2 Notes 5A-5B)

  • Secondary and service tags installed (Marking 033582 Rev.07: Pgs. 2-3 Note 7)

  • CIC requires 1 tag per conductor (Marking 033582 Rev.07: Pgs. 1-2 Note 5 A(1))

  • Mounting bolts for temporary parking stand installed; 600T w/200-amp separable connections (Terminations 051071 Rev.11: Pg. 2 Note 2 L-M, Pg. 9 Note 3)

  • Spare ducts plugged properly (Conduits 062288 Rev.18: Pg. 1 Note 8; Transformers 045292 Rev.12: Pg. 2 Note 21)

  • Cables/conduits sealed per standard ( Cable 057837 Rev.00; General 76264 Rev.01; Conduits 062288 Rev.19: Pg. 2 Note 11, Pgs. 19-22)

  • Cable protector or duct terminators Installed (Conduits 062288 Rev.19: Pg. 2 Note 18; Transformers 045292 Rev.13: Pg. 2 Note 22).

  • Fault indicators installed as required (General 061683 Rev.17)

Primary Terminations

  • Primary terminations?

  • (Grey Item) Bleeder wire(s) installed (Terminations 035314 Rev.15: Pg. 16 Step 16; TD-035314B-008 Rev.0).

  • (Grey Item) Capacitance test cap installed (Terminations 035314 Rev.15: Pg. 16 Step 18)

  • (Grey Item) Hold down bail secure and on straight (Terminations 035314 Rev.15: Pg. 17 Step 20)

  • Operable with adequate movement (Terminations 035314 Rev.15: Pg. 15 Step 1; Terminations 051071 Rev.11: Pg. 2 Note 2 L; Switches 039954 Rev.10: Pg. 4 Note 2 E (4); Switches 050859 Rev.18: Pg.5 Note 12 D)

Comments and Signature

  • Notification created?

  • Provide notification # if available

  • Comments

  • Crew Lead or Supervisor Work Verification?

  • Note: The supervisor's signature is not required on the crew lead's CCSC Form

  • LAN ID

  • Full Name and Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.