Title Page
-
Site conducted
-
Conducted on
-
Conducted by:
-
VRM
-
Fleet Number
-
ODO Reading
-
Lift Make
-
Lift Model
-
Lift Serial Number
-
SWL
Six Month LOLER Inspection
-
1, Remove beam or ram cover (refit)
-
2, Check ram(s) - Leaks & operation
-
3, Check power pack - Leads and operation
-
4, Check all hydraulic valves
-
5, Check Pipes and Hoses - Leaks and condition
-
6, Check banjo and couplings - Leaks
-
7, Check safety catch - wear and condition
-
8, Check safety gates
-
9, Check runner bearings
-
10, Check pivot pins & shaft - Alignment and wear
-
11, Check guide rollers (tuck away)
-
12, Check platform alignment with floor
-
13, Check stow lock device - wear and condition
-
14, Check L.S.D of C.F.D - Operation
-
15, Check stow gaurd - Security and clearance
-
16, Check platform rubber buffer - wear/security
-
17, Check platform anti-tilt device - Operation
-
18, Check loading ramp - wear
-
19, Check platform wear and condition
-
20, Check all welds - Cracks and condition
-
21, Check int/ext control box - condition and security
-
22, Check isolator and limit switches - condition
-
23, Check wander lead - Operation and condition
-
24, Check wiring and main cables - Security and condition
-
25, Check power pack mounting - Security
-
26, Check inline fuse/holder - Condition
-
27, Check operation sticker - Fitted, visible and clear.
-
28, Check marker light/flag - Operation and condition
-
29, Check circuit boards - Security/operation
-
30, Other
LOLER Declaration
-
This equipment is now of a satisfactory standard and is fully functional for service
-
This equipment has not been fully repaired and the following action must be taken
-
Apply an immediate repair to allow a safe operation of unit
-
Remove the unit from service until repair has been effected
-
Continue to use equipment. Repair at next service plan
-
Pass or Fail LOLER check?
-
I certify that the passenger lift was thoroughly examined on the above date and that subject to any remedial action noted is safe to operate. Engineers signature
-
Date of examination
-
Date of next examination
Weight Test Certificate
-
Safe Working Load (KG)
-
Downward creep in 10 minutes (MM)
-
Operation time in SWL UP (seconds)
-
Operation tome in SWL DOWN (seconds)
Declaration
-
I Certify on this date the above equipment was tested.
-
Date