Title Page
-
Site
-
Permit Number
-
Completed by:
-
Trade-Contractor
-
Permit Issued to (Responsible Person):
-
Permit Validity ( 5 Days ) No weekend working around services - From:
-
Until:
-
Safe System of Work Name and Number:
Part 1
-
Location, Extent of Permit & Brief Description of Work (Work zone to be clearly marked on a drawing)
Part 2
-
MASTER DRAWING - The following known services have been identified in the master drawing - ( Utility drawing / GPRS not to be older that 6 months )
- Underground Electrical
- Gas
- Water
- Telecom
- Surface/Sewer
- Overhead Electrical
- Other (state)
Part 3 - Control Checks
-
Has the relevant work area been visually surveyed and fully scanned using scanning equipment including signal generator (all modes) minimum eCAT4+
-
Serial Number
-
Calibration Date
-
All modes used?
-
Scanning Completed by? (Have they been trained in use of the CAT & Genny?)
-
Have the locations of all identified utilities been physically marked on the ground ?
-
Has the scanning equipment identified the location of any uncharted utilities?
-
If no utilities have been located, shown on drawings or there is no evidence proceed to Green Permit but proceed with caution scanning the ground every 300mm.
-
Has the correct PPE i.e. Flame retardant coveralls/gloves and electrically insulated tools been issued as per risk assessment?
-
Have any isolations requested been granted and in place ( Copy of isolation certificate required / or physical proof )
-
Details of Confirmation
-
Has the work area been suitably segregated?
-
Is support and protection equipment available if services are to be exposed over a considerable distance?
-
Items Issued:
-
Has a colour drawing / sketch of services with physical reference points noting the trial hole / slit trenches been prepared and attached to this permit
4 Site Manager / Supervisor & Responsible Person Acceptance
-
To be completed By the Responsible Person to confirm that the aforementioned sketches and controls have been accepted:
-
Site Manager / Supervisor
-
Responsible Person
5 Briefing by Responsible Person to Dig Team
-
To be signed by all personnel involved in undertaking the works to confirm understanding of:
1 Safe System of Work and associated risk assessment.
2 The aforementioned sketch and controls.
3 Prohibition on the use of mechanical plant/equipment with this permit unless it is non-contact i.e. vacuum excavation or hand digging using insulated tools / equipment
4 If trial hole / slit trench has to go through tarmac / concrete where it is not 500mm below the surface then following the marking out of the existing services on the ground a minimum of 500mm away from the service/s a saw cut can be made which will allow tunnelling in from the side.
5 If trial hole / slit trench is of considerable depth which would require the area to be stepped to provide safe access and also support during the works please STOP work and move to a Green permit. -
NOTE: ALL UTILITIES MUST BE TREATED AS LIVE – IF YOU ENCOUNTER HARD SURFACES, SUCH AS CONCRETE, STOP WORK IMMEDIATELY AND SEEK FURTHER ADVICE FROM YOUR SITE MANAGER / SUPERVISOR
-
Name of Employee
-
Name of Employee
-
Name of Employee
-
Name of Employee
-
Name of Employee
-
Name of Employee
-
Name of Employee
6 Daily Compliance Check by Site Manager / Supervisor
-
Date, Time and Initials (in notes)
-
Date, Time and Initials (in notes)
-
Date, Time and Initials (in notes)
-
Date, Time and Initials (in notes)
-
Date, Time and Initials (in notes)
-
Date, Time and Initials (in notes)
-
Date, Time and Initials (in notes)
7 Completion Checks
-
Trial Hole 1
-
Trial Hole 2
-
Trial Hole 3
-
Trial Hole 4
-
Trial Hole 5
-
Have all the trial holes / slit trenches located the known services which were highlighted in Section 1&2?
-
What has been done to prove that there are no services in the line of the proposed excavation?
-
Have all the services found been surveyed and plotted on an As-built?
8 Dig team carrying out the work must inform the site manager / supervisor of any additional findings or variances
-
Additional Findings - not shown on, or variances relating to, the service(s) sketches:
9 Site Manager / Supervisor Confirmation that the mast drawing(s) has been updated with co-ordinates/depth
-
Site Manager / Supervisor
Cancellation
-
The works have been completed/stopped and this Permit is cancelled
-
Site manager / Supervisor