Title Page

  • Audit Category

  • Audit Title

  • Conducted On

  • undefined

DETAILS OF WORK

  • Plant/Equipment Name

  • Location of Work

  • Description of Work

  • Date of Work

  • Expected duration of Work

CRANES AND LIFTING EQUIPMENT TYPES

  • Forklift JIB

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Lifting Gantry Crane

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Stable Ground for Crane Setup

  • Safe Work Load Tags Sighted and Certification made Available

  • Please See Manager

  • Exclusion zone is sufficient to eliminate risk form falling objects

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane operator holds license for the correct class or crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Load will not Pass over workers in Internal Buildings or offices

  • Notify to Manager and Office Staff

  • Operators have completed Cranes & Lifting Appliances training

  • DO NOT OPERATE CRANE OR APPLIANCES

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane is Appropriate Size for the Loads and reaches of the Task

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane's Outrigger Legs Suitably Extended to Support the Crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All External Doorway Access in Area is Roped off

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All Personnel on site notified that the area is "NO-GO" Zone.

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Tag Lines are Available if required

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Mobile Lifting Crane

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Stable Ground for Crane Setup

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Safe Work Load Tags Sighted and Certification made Available

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Exclusion zone is sufficient to eliminate risk form falling objects

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane operator holds license for the correct class or crane

  • DO NOT OPERATE CRANE

  • Load will not Pass over workers in Internal Buildings or offices

  • Notify to Manager and Office Staff

  • Operators have completed Cranes & Lifting Appliances training

  • DO NOT OPERATE CRANE OR APPLIANCES

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane is Appropriate Size for the Loads and reaches of the Task

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane's Outrigger Legs Suitably Extended to Support the Crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All External Doorway Access in Area is Roped off

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All Personnel on site notified that the area is "NO-GO" Zone.

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Tag Lines are Available if required

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Long JIB

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Stable Ground for Crane Setup

  • Safe Work Load Tags Sighted and Certification made Available

  • Please See Manager

  • Exclusion zone is sufficient to eliminate risk form falling objects

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane operator holds license for the correct class or crane

  • DO NOT OPERATE CRANE

  • Load will not Pass over workers in Internal Buildings or offices

  • Notify to Manager and Office Staff

  • Operators have completed Cranes & Lifting Appliances training

  • DO NOT OPERATE CRANE OR APPLIANCES

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane is Appropriate Size for the Loads and reaches of the Task

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane's Outrigger Legs Suitably Extended to Support the Crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All External Doorway Access in Area is Roped off

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All Personnel on site notified that the area is "NO-GO" Zone.

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Tag Lines are Available if required

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Small Lifting Crane

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Stable Ground for Crane Setup

  • Safe Work Load Tags Sighted and Certification made Available

  • Please See Manager

  • Exclusion zone is sufficient to eliminate risk form falling objects

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane operator holds license for the correct class or crane

  • DO NOT OPERATE CRANE

  • Load will not Pass over workers in Internal Buildings or offices

  • Notify to Manager and Office Staff

  • Operators have completed Cranes & Lifting Appliances training

  • DO NOT OPERATE CRANE OR APPLIANCES

  • Crane is Appropriate Size for the Loads and reaches of the Task

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane's Outrigger Legs Suitably Extended to Support the Crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All External Doorway Access in Area is Roped off

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All Personnel on site notified that the area is "NO-GO" Zone.

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Tag Lines are Available if required

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Lifting JIB

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Stable Ground for Crane Setup

  • Safe Work Load Tags Sighted and Certification made Available

  • Please See Manager

  • Exclusion zone is sufficient to eliminate risk form falling objects

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane operator holds license for the correct class or crane

  • DO NOT OPERATE CRANE

  • Load will not Pass over workers in Internal Buildings or offices

  • Notify to Manager and Office Staff

  • Operators have completed Cranes & Lifting Appliances training

  • DO NOT OPERATE CRANE OR APPLIANCES

  • Crane is Appropriate Size for the Loads and reaches of the Task

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane's Outrigger Legs Suitably Extended to Support the Crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All External Doorway Access in Area is Roped off

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All Personnel on site notified that the area is "NO-GO" Zone.

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Tag Lines are Available if required

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Dogmen/ Rigger

  • Please Refer SOP or JSEA from Crane Provider

  • Please Fill JSEA

  • Job Details

  • Location of Work

  • JSEA Developed by

  • Date

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Personnel Involved in Activity

  • Name of Relevant Worker

  • Qualification / Licenses / Ticket Held

  • Signature

  • Common Hazards

  • Work Environment/Site Layout

  • Working from Height

  • Ground Surface

  • Stability

  • Security

  • Vibration

  • Confined Spaces

  • Site Access/Egress

  • Underground Hazards

  • Lighting

  • Mobil Plant/Pedestrians

  • House Keeping

  • Asbestos

  • Thermal Comfort

  • Slips & Trips

  • Overhead Hazards

  • Site induction

  • Chemical

  • Biological

  • Fire/Flammability

  • Corrosive

  • Compatibility

  • Labelling

  • MSDS Available

  • Absorption

  • Inhalation/Ingestion

  • Signage

  • Spill Control

  • Storage

  • PPE Available

  • Manual Handling

  • Repetitive Actions

  • Cold/Hot

  • Lifting/Carrying

  • Bending/Reaching

  • Excessive Distances

  • Awkward Postures

  • High Forces- Heavy Load

  • Pushing/Pulling

  • Restraining/Supporting

  • Stability/Size of Load

  • Plant

  • Crushing

  • Cutting/Stabbing

  • Electrical

  • Entanglement

  • Falling

  • High Pressure

  • Hot Surfaces

  • Isolation

  • Maintenance

  • Noise

  • Pre-start Checks

  • Striking

  • Signage

  • Safe Work Procedures

RISK MATRIX

  • HSW RISK MATRIX

JOB SAFETY ANALYSIS

  • Job Safety Analysis

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Task

  • Hazards

  • Potential Risk Score

  • Risk Control Measures

  • Residual Risk Score

  • Responsible Person

  • Weather Conditions are suitable for work

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Barricades and Signage are Available and in Place

  • Work Complies with NSW overhead power line Code of practice

  • Follow NSW overhead power line Code of Practice

  • PPE has been checked and is Appropriate

  • Stable Ground for Crane Setup

  • Safe Work Load Tags Sighted and Certification made Available

  • Please See Manager

  • Exclusion zone is sufficient to eliminate risk form falling objects

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane operator holds license for the correct class or crane

  • DO NOT OPERATE CRANE

  • Load will not Pass over workers in Internal Buildings or offices

  • Notify to Manager and Office Staff

  • Operators have completed Cranes & Lifting Appliances training

  • DO NOT OPERATE CRANE OR APPLIANCES

  • Crane is Appropriate Size for the Loads and reaches of the Task

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Crane's Outrigger Legs Suitably Extended to Support the Crane

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All External Doorway Access in Area is Roped off

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • All Personnel on site notified that the area is "NO-GO" Zone.

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Tag Lines are Available if required

  • Suspend Permit, Please check with Permit Issuer/ Manager

  • Dogmen/ rigger Qualifications Documentation/ license

  • DO NOT OPERATE DOGMEN/RIGGER

  • Suspend Permit, Please check with Permit Issuer/ Manager

IDENTIFY AND ISOLATE ENERGY SOURCES

  • Isolation Required

  • Electrical

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Pneumatic

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Hydraulic

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Stored Energy (Compressed Spring, Compressed Air, Hydraulic Pressure, Fluid Pressure)

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Fluid (Chemical, CIP, Product, Hot Water, Cold Water)

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

ISOLATION REGISTER

  • Isolation Required

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Isolation Required

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Isolation Required

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

  • Isolation Required

  • Employee Name

  • Plant/Equipment Name

  • Time Locks were attached

  • Time Locks were removed

  • Signature

AUTHORISATION

  • I have reviewed the hazards and control measures documented in the relevant JSEA/SOP for this task. I believe that the work can be completed safely provided all the above-mentioned precautions and the relevant JSEA/SOP are complied with

  • Permit Issuer

  • Permit User

  • Permit User

  • Safety Observer

  • Name and Signature

PERMIT SUSPENSION

  • The permit has been suspended due to work not being completed. The following precautions have been completed in the work area

  • Area access restricted

  • Isolation retested

  • Equipment Secured

  • Signage in place

  • Area Manager notified

PERMIT REVALIDATION

  • This Permit has been revalidated to allow suspended work to be recommenced. The following precautions have been completed

  • Area Inspected

  • Environmental conditions safe

  • Pre-start checks completed

  • Area Manager notified

  • Permit Issuer

  • Permit User

COMPLETION OF WORK VERIFICATION

  • I have inspected the work area and certify that all personnel, tools and equipment have been removed from the area, all guards and covers have been replaced, all LOTO devices have been removed and all barriers and notices removed. I confirm that the area is safe for normal operations to resumes.

  • Permit Issuer

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.