Title Page

  • Site conducted

  • Document No.

All accidents are avoidable. You have a responsibility to safeguard yourself and others who may be affected by your actions. No work must take place until this Permit has been completed in full and signed by an Authorised Person.

Section1: Site and Location

  • Site/Location

  • Contractor

  • Brief description of work

  • Conducted on

  • Prepared by

  • Names of Engineers

Permit

Section 2: Precautions and Control Measures

  • Relevant and suitable written system of isolation available and reviewed?

  • Supplementary Fire Risk Assessment completed prior to works commencing?

  • All ancillary services (electric/water/gas) isolated as required?

  • Temporary fire detection/fire fighting equipment in place?

  • Suitable fire watch arrangements in place?

  • Landlord/Insurers and any other parties that may be affected informed of works?

  • Any other systems affected by the isolation/works identified and control measures in place?

  • Risk Assessment/Method Statement attached to permit?

  • All personnel involved understand the local Emergency Procedures?

  • Site Fire Log Book completed indicating isolations?

If the answer to any of the applicable questions is 'no' then you must not authorise the permit, but take corrective actions. If you are unsure about any aspect then you should not authorise the permit and seek further advice/guidance.

  • Additional information on any of the above or any relevant issues:

Section 3: Authorisation of Permit

I declare that the above control measures are in place and communicated to the Competent Person in charge of the work

  • Authorised Person:

  • Mobile Number:

  • Valid From:

  • Valid To:

Section 4: Acceptance of Permit by Competent Person in Charge

I acknowledge receipt of this permit and understand the safety precautions described above. I will adhere to the Method Statement and neither I, nor any person under my control will work on any other equipment. I will return this Permit to the Approved Person.

  • Competent Person:

  • Mobile number:

Section 5: Time Extension (can only be granted by the Approved Person who issued the Permit)

  • Authorised Person:

  • To:

Section 6: Completion of Works

I declare that the work detailed in section 1 has been completed or that no further work will take place until a new Permit is issued. The work area has been left safe, clean and tidy and equipment is safe to return to service unless otherwise stated.

  • Competent Person:

  • Time/Date:

Section 7: Permit Closure

  • Authorised Person:

  • Date/Time

Once the Permit has been closed, no further work activity can be undertaken and no return to high risk area is permitted.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.