Title Page
-
Site conducted
-
Project Number
-
Conducted on
-
Prepared by
-
Location
-
Field Number
-
Row Inspection Started
-
Row Inspection Finished
Piling Inspection
Piling Inspection
-
Pile height tolerance is within 25% of pile measurement above<br>ground as per Solarport manual - 125mm
-
Front and rear legs are correctly installed as per Solarport manual
-
Front and rear posts are not twisted more than the tolerances in Solarport manual
-
Pile verticality is within the tolerances stated in Solarport manual
-
Piles have been rammed using a string line to ensure line and level is correct
-
Pile spacing is as per Solarport manual
-
Any damaged pile heads have been repaired
-
All piles heads have had zinc paint applied.
-
All measurements have been checked and are as stated in Solarport manual.
-
PERFORMED BY:
-
DATE: