Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Contract No.:
-
Site Name:
Work Area:
-
Site Manager:
-
External Parties:
-
Piepwork Contractor:
-
Audit no.:
-
Date/Time:
-
Weather:
-
Carried by:
Section I - General site checks
-
Fittings off the floor and stored on shelf, gaskets and bolts wrapped, ends protected. Clean pipework working area
-
No chemicals stored near the pipe storage area
-
Work areas kept tidy and appropriate signs used
Personnel
-
Site team are using the latest drawings
-
Pipefitters have access to Client specifications
-
Pipefitters have the appropriate CSCS Card
-
Pipefitters have a EUSR Clean Water Card
-
Pipefitters have relevant client training
-
Have been briefed on the RAMS and signed
-
Use of gloves when handling fittings
-
Pipefitters have the Flanged Joint Training
-
Pipefitters have the Butt-Fusion Training
-
Pipefitters have the Electrofusion Training
Materials
-
Supplied by framework supplier otherwise approved by Client/Barhale
-
No faulty fittings were encountered through the project
-
Materials used for backfill as per Client specification
-
Traceable marker tape used as per Client specification
-
End caps on as long as possible to prevent contamination and pipe stoppers uesd
-
Pipes/fittings free from damage or defects prior to being laid
-
Any repairs made in accordance with design specification and manufacturers guidance
-
Section IV - Plant and equipment
-
Pipework equipment checks being carried out regularly
-
Lift plan contains details of the correct lifting equipment for pipework
-
Plant, equipment and tools used for installing and testing have been inspected/certificated
Quality
-
Suitable ITP for pipework installation
-
Client specific work permits in place
-
Pipes installed at the correct depth / gradient
-
Any deviations from construction drawings signed-off by designer/ client
-
Minimum distance between joints as per design and specifications
-
Recommended pipe bedding and surround in place as per client standards
-
Apparatus installed as per client specification ( washout, covers, marker plates )
-
Thrust blocks and pipe restraints as per design
-
Use of lubricant before torqueing the bolts
-
Flanged joined records available and in use
-
Calibration certificates for torque spanners in date
-
Evidence of Buried Joint Protection (Denso)
-
Approval for using electro-fusion obtained
-
Evidence of the installation markings done on the pipe
-
Use of welding tent when weather conditions require it
-
PE welding equipment being used with CONTROL POINT system, BDI data downloaded for ITP
-
Use of turfers and round slings for pulling pipes where pushing not possible/recommended
-
Use of the correct type of gaskets as per design
Section VI - Testing and Commissioning
-
The ground doesn’t have any signs of contamination
-
Swabbing equipment on site and correctly used
-
Approved ITP for pressure testing pipelines in place
-
Test Plates are kept bagged and stored safely
-
Existence of chlorination procedures being done
-
Acceptable source of water being used for filling and flushing the main