Post-rainfall inspection (>10mm in 24hrs)

  • Last rainfall date:

  • Rainfall volume:

  • Zones / Areas inspected:

  • Conducted on

  • Prepared by

  • Personnel

General

  • ERSED - Do any erosion controls require maintenance or repair to prevent soil loss before the next rain event? e.g. whoa boys, rock lined drain

  • ERSED - Do any sediment controls require cleaning out or reinstating to prevent soil loss before the next rain event? e.g. sumps, sed fences, coir logs, etc

  • If outlet controls have failed / overtopped, have receiving water bodies been inspected and evidence collected ?<br>(Water Quality samples, GPS coordinates, photos)

  • Do ERSED controls need cleaning out or to be repaired or maintained?<br>(If controls have less than 30% capacity answer Yes)

  • Crossings / Waterways - has any erosion been caused within the crossing and or the batters and banks?

  • Have the crossings been stabalised with protective measures e.g. geo-fab, soil binder, flexterra?

  • Has background water monitoring been taken? Has there been any increase in turbidity due to construction works?

  • Do rehabilitated areas have any signs of erosion and or scouring?

  • Do any bellholes, open excavations or low points need dewatering?

  • If answer is Yes (above), has a suitable discharge location been identified, controls procured and crew trained?

  • Has Water Release Approval been issued for all dewatering activities?

  • Are additional controls required to be installed before waters can be discharged?

  • RoW Boundary - Are there any signs of failure of controls resulting in uncontrolled dirty water or sediment discharging from site?

  • Bunding - Has any bunded pallets or spill trays filled with water?

  • Exclusion Zones - Are all exclusion zones clearly flagged off and signed?

  • Stockpiles - Are stockpiles adequately protected or stabilised to prevent soil erosion?

SUMMARY

  • Has any sediment left site? To what extent has this occurred? What are the actions required to rectify the issue?

  • Have photos been taken of areas where works or maintenance is required?

  • Has an Environmental Action list been prepared and register been updated?

  • Do ERSED Plans need to be updated or ECDNs be raised?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.