Information
-
Devine Homes Site Address
-
Conducted on
-
Prepared by
-
Location
WHS Practical Completion Review
Approve Site WHS Management Plan
-
There was a Site WHS Management Plan, approved by a Devine Homes Site Manager (for subcontractor access) prior to commencement of construction?
Review Safe Work Method Statements (SWMS)
-
There was a Safe Work Method Statement (SWMS) provided to the Site Manager for high risk activities conducted on site? (Use of mobile plant, work at heights, electrical installations etc)
Participate in site based WHS program's
-
Records of Devine's involvement in on site WHS program's including;
-
Site inductions; there were records of workers having signed Appendix C of the Site WHS Management Plan?
-
Weekly Site Inspections conducted by the Site Manager?
-
Site Toolbox Talks were conducted on site if applicable? (National EHS Manager will issue an instruction if a toolbox talk is to be conducted)
-
Incident Reporting and Incident Investigation was conducted (if applicable)?
WHS Inspections, Audits
-
Actions identified from site inspections or audits have been closed out?
Approval
-
Site Manager Name
-
Add signature
-
Select date