Information
-
Inspection Title: H2A USE, INSTALLATION, INSPECTION AND/OR REPAIR OF PLANT AND EQUIPMENT .
-
Project Name: Tabulam New Bridge.
-
Location: BRUXNER HIGHWAY TABULAM
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
-
References:
WHS Regs. Chapter 5, Part 5.1, 5.2, 5.3 – s186-s288
G22 – In complete and Annexure G22/J – Truck & Plant Requirements
There are numerous Codes of Practice that relate to Plant & Equipment – WorkSafe NSW has the documents available on their website:
http://www.safework.nsw.gov.au/law-and-policy/legislation-and-codes/codes-of-practice
Additionally there are numerous Australian Standards that should be reviewed for information and specification requirements for specialised plant and equipment. Discuss with WHS Partner. -
N.A. Not Applicable N.C. Not Checked
1 Have foreseeable hazards from the operation of plant/equipment been assessed, including the following:
-
<br> Contact or entanglement with the machinery or materials?<br>
-
Being trapped between the machine and any material or fixed structures?
-
Being struck by ejected material from the machinery?
-
Noise and vibration from the machinery?
-
Release of potential energy?
-
2<br>Have the design limitations of the machine been assessed, with regard to the intended use of the machine?
-
3<br>Has any history of unsafe incidents or adverse health effects involving the plant/equipment been investigated and control responses applied?
-
4<br>Have the consequences of reasonably foreseeable misuse or malfunction been assessed?
-
5<br>Has a schedule of inspection, maintenance, repair and cleaning been developed for all plant/equipment?<br>
-
6<br>Are records kept of inspection
-
7<br>Were risk assessments carried out on any modification to plant/equipment and the results of the risk assessment taken into account in the final modification?
8 Have all operators of plant/equipment:
-
<br> Received the appropriate training,<br>
-
Hold certificates of operation where required,
-
Demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor?
-
9<br>Are records kept to show that all operators have received appropriate training and instruction?
Compliance and Follow-up action.
-
Is the activity compliant.
-
Surveillance Officer
-
NCPN or memo number.
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
RMS representative's name