Inspection Title. RMS Surveillance Checklist R11- Stormwater Drainage -Pipes ILC-MI-TP3-405-SC-R11- Open drains Ed 5 / Rev1
-
Project Name: Tabulam New Bridge.
-
Location: BRUXNER HIGHWAY TABULAM
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
4.1.1 Setting Out
-
Is the set out the stormwater drainage systems as shown on the Drawings and in sufficient detail to identify:<br>(d) the locations and levels of open drains.
-
Has the Hold point point been released
4.2 CONSTRUCTION OF OPEN DRAINS
-
Are open drains excavated (including topsoil) to the dimensions shown on the Drawings.
-
Where dimensions are not shown, the open drain must have a minimum depth of 300 mm, a minimum waterway area of 0.2 m2, with side batter slopes not steeper than 2H:1V.
-
Grade the open drains to a slope of not less than 0.5% to ensure a free flow of water. Where this is not feasible, notify the Principal. Has the hold point been released
-
Has the trimmed surface of excavated open drains to a depth of 150 mm, before placing lining or spreading topsoil for vegetation or fill material in embankments of open drains been compacted to 95%
-
Where construction of an embankment is required to form an open drain, clear, grub and strip of topsoil the affected area prior to placing the fill material.<br>Place fill material complying with Clause 3.3 in layers not exceeding 200 mm in depth, and compact to 95%.
-
(b) a Plasticity Index, as determined by Test Method RMS T109, of between 15 and 30.
-
Unless otherwise shown on the Drawings or directed by the Principal, line open drains with:<br>(a) organic fibre mat and vegetation, where the longitudinal grade of the completed drain is between 1% and 5% inclusive; or
-
(b) concrete where the longitudinal grade of the completed drain is less than 1% or greater than 5%.
-
Concrete lining must have a minimum compacted thickness of 100 mm measured at right angles to the surface of the lining,
-
Have rock mattresses been used only where shown on the Drawings.
-
Have movement joints been placed in concrete lining at intervals of not more than 3.0 m along the open drain to control cracking.
-
Install expansion joint material complying with RMS 3204 to the full depth of the concrete lining at every fifth movement joint.
-
Does the open drain conform to construction tolerances in table R11.4
G22 Safety and G36 Environmental
G22 SAFETY
-
Has a safe work and technical criteria been implemented for the connection of existing pipes to new pipes that have the same or grater size.
-
Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>
-
Has a SWMS been developed.
-
Is each and every item of plant being used for its designated and intended purposes.
-
Have the attachments for plant and processes been approved and used in accordance with their design and purposes.
-
Is the correct PPE being worn
-
Is the laser used approved for use.
-
Is all lifting plant fitted with approved hooks/lugs and its SWL marked.
-
Has safe entry/ exit been provided to excavations.
-
Has the excavation been battered/benched if depths greater than 1.5m, or if there is a possibility of collapse.
-
Has spoil been placed away from the excavation.
-
Were any unsafe practices observed. <br>
-
Good safe practices observed.
G36 ENVIRONMENTAL
-
R44 Cl 1.7 Were erosion and sediment controls in place prior to the removal of any topsoil.
-
Are Erosion and Sediment controls measures being installed prior to works commencing and are they being maintained.
-
Has mud been prevented from being deposited on roadways.
-
Have any environmental incidents or potential incidents been observed.
-
Good environmental procedures observed.
Compliance and Follow-up action.
-
Is the activity compliant.
-
Surveillance Officer
-
NCPN or memo number.
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
RMS representative's name