Information
-
Client / Site
-
Project Job no.
-
Is a workshop number required?
-
Is an Electrical division number required?
-
Site address
-
Accountable Director
-
Operations Manager
-
Estimator
-
Project Manager
-
Quantity Surveyor
-
H&S
-
Site Manager
-
Start on site date
-
Handover date
-
Project duration (weeks)
Milestone 1 - Invitation to tender
-
Invitation to tender received - Estimator
-
Project Appraisal - Director
-
Bid / No bid - Director
-
Credit Check - Director
-
ISV to determine scope - Estimator
-
Condition photo log of all areas - Estimator
-
Populate BoQ/Schedule - Estimator
-
Complete PQQ (if required) - Estimator
-
Complete RFI sheet - Estimator
-
Complete contractors proposal - Estimator
-
Save all tender notes and photos to server - Estimator
Milestone 2 - Tender Submission
-
Issue tender to client - Estimator
-
CVR profit plan compilation - Estimator
-
Tender adjudication - Estimator
-
Response of tender status? - Quantity Surveyor
Milestone 3 - Cost Approval
-
Receipt of construction drawing set - Estimator
-
Check construction drawings compared to tender drawings - Estimator
-
Split into work packages and send out to subcontractors - Estimator
-
Value engineering to drawings - Estimator
-
Receipt of RFI's from subcontractors and send client - Estimator
-
Complete cash flow document - Estimator
-
Receive requested additional information from client - Estimator
-
Supply requested information to subcontractors - Estimator
-
Firm up all provisional sums with subcontractors - Estimator
-
Make changes to BoQ where required (incl. prov sums) - Estimator
-
Compile draft programme of works incl. Phasing plan (if req) - Project Manager
-
Complete Labour model - Project Manager
-
Re-submit to client for approval incl. Programme - Estimator
-
Receipt of contract documents and supply to director to sign - Estimator
-
Sign and return contract documents post legal review - Director
-
Verbal / Email confirmation of project secured?
Milestone 4 - Statutory Consents (Client direct or PO required separately)
-
Receipt of PCI - H&S
-
Internal Pre-con to Ops handover (if D&B) - Operations Manager
-
Iron out further queries from costs - Estimator
-
Request planning permission - Project Manager
-
Request landlord consent - Project Manager
-
Request Listed Building Consent - Project Manager
-
Request Scaffold Design - Project Manager
-
Request hoarding design - Project Manager
-
Specialist contractor design engagement (if required) - Quantity Surveyor
-
Engage with service providers - i.e. electric, gas, water, BT etc.. - Project Manager
-
Structural Engineer engagement - Quantity Surveyor
-
Request Environment Agency Permit - Quantity Surveyor
-
Highways works engagement - Project Manager
-
Fire risk assessor engagement - Project Manager
-
Request Building Control Engagement - Project Manager
-
Request Advertising consent - Project Manager
-
Specialist contractor intrusive/validation surveys - Quantity Surveyor
-
R&D survey to undertake - H&S
-
Temporary Works Register to compile - Project Manager
-
Receipt of scaffold design/confirmation of TG20:13 scaffold - Project Manager
-
Client CAPEX approval confirmation - Quantity Surveyor
Milestone 5 - Product Approval
-
Receipt of Purchase Order - Quantity Surveyor
-
Job number request sent - Quantity Surveyor
-
Internal Pre-con to Ops handover undertaken (if traditional) - Operations Manager
-
CVR review and amendment - Quantity Surveyor
-
Liaise with tender stage suppliers/subcontractors to validate/firm up quotes - Quantity Surveyor
-
Appoint a Site Manager - Operations Manager
-
Client to supply contact list of direct contractors - Project Manager
-
Compile Procurement Schedule - Quantity Surveyor
-
Place all subcontractor orders - Quantity Surveyor
-
Outstanding orders?
-
Structural engineer to approve scaffold design - Quantity Surveyor
-
Structural engineer to approve/supply hoarding design - Quantity Surveyor
-
M&E consultant to approve specialist designs - Project Manager
-
Request pavement/scaffold license - H&S
-
Long lead time materials ordered with buyers - Project Manager
-
When will they receive schedules?
-
Are any long lead time items going to cause project delays?
-
Which items and what is lead time?
-
Are long lead time materials ordered? - Project Manager
-
What is left to order?
-
Any items caused issues so far?
-
Are you awaiting any RFI's on specifications to be answered?
-
What do you need to know?
-
Have all dimensions/quantities been supplied?
-
What is outstanding?
-
Have all manufactured items been ordered?
-
Why?
-
When will they be ordered?
-
Is this in house or outsourced workshop?
-
Have workshop hours and dates been agreed?
-
What are agreed hours?
-
Is workshop happy with required delivery dates?
-
Do workshop know how many deliveries have been allowed for in tender?
-
Do they have all information to manufacture items?
-
What information is required?
-
When will these be agreed?
-
Have all critical dims been supplied?
-
What is outstanding?
-
R&D report received and reviewed? - H&S
-
When will this be reviewed?
-
Any Asbestos to note?
-
Is any of the asbestos notifiable?
-
Supply Project Manager and H&S with compiled subcontractor contact list - Quantity Surveyor
-
Confirm whether any samples are required, compile sample schedule and send to buyers - Project Manager
-
Complete Construction issue Programme of Works and Phasing Plan (if req) - Project Manager
-
Ensure all pavement licenses etc.. are received and inform PM - H&S
-
Send Site file request and site setup email to all internal departments - Project Manager
-
Request delivery map from buyers - Project Manager
-
Distribute programme of work to all direct contactors with delivery map and RAMS request - Project Manager
-
Send email to all domestic subcontractors with programme, delivery map and RAMS request - Project Manager
Milestone 6 - Pre-construction approval and mobilisation
-
CPP to complete - H&S
-
RAMS from all appointed subcontractors chased - H&S
-
Fire Risk assessment - H&S
-
Confirmation of site permit requirements - H&S
-
Fire Action Plan - H&S
-
Traffic management plan - H&S
-
Site Set-up Plan - H&S
-
Any site constraints to note?
-
Ops to site handover - Project Manager
-
Project Pack collation - Project Manager
-
Plant and delivery model - Project Manager
-
Welfare and Site Setup checklist - Project Manager
-
Receipt of Temporary Works Design (if required) - Project Manager
-
Project Managers collated labour model review - Operations Manager
-
Supply all required H&S documentation to client for comment - H&S
-
Any comments returned from client?
-
Appointment of Temporary Works Supervisor - Operations Manager
-
Site materials and manufacture orders validated - Project Manager
-
Master Programme updated - Operations Manager
-
Site Starter pack order - Project Manager
-
F10 to submit (if required) - H&S
-
Collate Site H&S File - H&S
-
Collate admin site file, incl. drawings, programme, time sheets, scope of works, labour model etc.. - Admin
RACI
-
Team Sheet Requests undertaken by
-
Weekly reports undertaken by
-
Master Programme update by
-
Construction programme updates by
-
Pre-Start meeting to organise (if not already carried out)
-
Chase up confirmation on supplied samples and order accordingly - Project Manager
-
Handover file request by
-
Ops to site handover to be carried out by
-
RFI schedule to be completed by
-
Precon to Ops Health Check review updated by
-
To have discussion with Site Manager on weekend working and labour model