Information

  • Client / Site

  • Project Job no.

  • Is a workshop number required?

  • Is an Electrical division number required?

  • Site address
  • Accountable Director

  • Operations Manager

  • Estimator

  • Project Manager

  • Quantity Surveyor

  • H&S

  • Site Manager

  • Start on site date

  • Handover date

  • Project duration (weeks)

Milestone 1 - Invitation to tender

  • Invitation to tender received - Estimator

  • Project Appraisal - Director

  • Bid / No bid - Director

  • Credit Check - Director

  • ISV to determine scope - Estimator

  • Condition photo log of all areas - Estimator

  • Populate BoQ/Schedule - Estimator

  • Complete PQQ (if required) - Estimator

  • Complete RFI sheet - Estimator

  • Complete contractors proposal - Estimator

  • Save all tender notes and photos to server - Estimator

Milestone 2 - Tender Submission

  • Issue tender to client - Estimator

  • CVR profit plan compilation - Estimator

  • Tender adjudication - Estimator

  • Response of tender status? - Quantity Surveyor

Milestone 3 - Cost Approval

  • Receipt of construction drawing set - Estimator

  • Check construction drawings compared to tender drawings - Estimator

  • Split into work packages and send out to subcontractors - Estimator

  • Value engineering to drawings - Estimator

  • Receipt of RFI's from subcontractors and send client - Estimator

  • Complete cash flow document - Estimator

  • Receive requested additional information from client - Estimator

  • Supply requested information to subcontractors - Estimator

  • Firm up all provisional sums with subcontractors - Estimator

  • Make changes to BoQ where required (incl. prov sums) - Estimator

  • Compile draft programme of works incl. Phasing plan (if req) - Project Manager

  • Complete Labour model - Project Manager

  • Re-submit to client for approval incl. Programme - Estimator

  • Receipt of contract documents and supply to director to sign - Estimator

  • Sign and return contract documents post legal review - Director

  • Verbal / Email confirmation of project secured?

Milestone 4 - Statutory Consents (Client direct or PO required separately)

  • Receipt of PCI - H&S

  • Internal Pre-con to Ops handover (if D&B) - Operations Manager

  • Iron out further queries from costs - Estimator

  • Request planning permission - Project Manager

  • Request landlord consent - Project Manager

  • Request Listed Building Consent - Project Manager

  • Request Scaffold Design - Project Manager

  • Request hoarding design - Project Manager

  • Specialist contractor design engagement (if required) - Quantity Surveyor

  • Engage with service providers - i.e. electric, gas, water, BT etc.. - Project Manager

  • Structural Engineer engagement - Quantity Surveyor

  • Request Environment Agency Permit - Quantity Surveyor

  • Highways works engagement - Project Manager

  • Fire risk assessor engagement - Project Manager

  • Request Building Control Engagement - Project Manager

  • Request Advertising consent - Project Manager

  • Specialist contractor intrusive/validation surveys - Quantity Surveyor

  • R&D survey to undertake - H&S

  • Temporary Works Register to compile - Project Manager

  • Receipt of scaffold design/confirmation of TG20:13 scaffold - Project Manager

  • Client CAPEX approval confirmation - Quantity Surveyor

Milestone 5 - Product Approval

  • Receipt of Purchase Order - Quantity Surveyor

  • Job number request sent - Quantity Surveyor

  • Internal Pre-con to Ops handover undertaken (if traditional) - Operations Manager

  • CVR review and amendment - Quantity Surveyor

  • Liaise with tender stage suppliers/subcontractors to validate/firm up quotes - Quantity Surveyor

  • Appoint a Site Manager - Operations Manager

  • Client to supply contact list of direct contractors - Project Manager

  • Compile Procurement Schedule - Quantity Surveyor

  • Place all subcontractor orders - Quantity Surveyor

  • Outstanding orders?

  • Structural engineer to approve scaffold design - Quantity Surveyor

  • Structural engineer to approve/supply hoarding design - Quantity Surveyor

  • M&E consultant to approve specialist designs - Project Manager

  • Request pavement/scaffold license - H&S

  • Long lead time materials ordered with buyers - Project Manager

  • When will they receive schedules?

  • Are any long lead time items going to cause project delays?

  • Which items and what is lead time?

  • Are long lead time materials ordered? - Project Manager

  • What is left to order?

  • Any items caused issues so far?

  • Are you awaiting any RFI's on specifications to be answered?

  • What do you need to know?

  • Have all dimensions/quantities been supplied?

  • What is outstanding?

  • Have all manufactured items been ordered?

  • Why?

  • When will they be ordered?

  • Is this in house or outsourced workshop?

  • Have workshop hours and dates been agreed?

  • What are agreed hours?

  • Is workshop happy with required delivery dates?

  • Do workshop know how many deliveries have been allowed for in tender?

  • Do they have all information to manufacture items?

  • What information is required?

  • When will these be agreed?

  • Have all critical dims been supplied?

  • What is outstanding?

  • R&D report received and reviewed? - H&S

  • When will this be reviewed?

  • Any Asbestos to note?

  • Is any of the asbestos notifiable?

  • Supply Project Manager and H&S with compiled subcontractor contact list - Quantity Surveyor

  • Confirm whether any samples are required, compile sample schedule and send to buyers - Project Manager

  • Complete Construction issue Programme of Works and Phasing Plan (if req) - Project Manager

  • Ensure all pavement licenses etc.. are received and inform PM - H&S

  • Send Site file request and site setup email to all internal departments - Project Manager

  • Request delivery map from buyers - Project Manager

  • Distribute programme of work to all direct contactors with delivery map and RAMS request - Project Manager

  • Send email to all domestic subcontractors with programme, delivery map and RAMS request - Project Manager

Milestone 6 - Pre-construction approval and mobilisation

  • CPP to complete - H&S

  • RAMS from all appointed subcontractors chased - H&S

  • Fire Risk assessment - H&S

  • Confirmation of site permit requirements - H&S

  • Fire Action Plan - H&S

  • Traffic management plan - H&S

  • Site Set-up Plan - H&S

  • Any site constraints to note?

  • Ops to site handover - Project Manager

  • Project Pack collation - Project Manager

  • Plant and delivery model - Project Manager

  • Welfare and Site Setup checklist - Project Manager

  • Receipt of Temporary Works Design (if required) - Project Manager

  • Project Managers collated labour model review - Operations Manager

  • Supply all required H&S documentation to client for comment - H&S

  • Any comments returned from client?

  • Appointment of Temporary Works Supervisor - Operations Manager

  • Site materials and manufacture orders validated - Project Manager

  • Master Programme updated - Operations Manager

  • Site Starter pack order - Project Manager

  • F10 to submit (if required) - H&S

  • Collate Site H&S File - H&S

  • Collate admin site file, incl. drawings, programme, time sheets, scope of works, labour model etc.. - Admin

RACI

  • Team Sheet Requests undertaken by

  • Weekly reports undertaken by

  • Master Programme update by

  • Construction programme updates by

  • Pre-Start meeting to organise (if not already carried out)

  • Chase up confirmation on supplied samples and order accordingly - Project Manager

  • Handover file request by

  • Ops to site handover to be carried out by

  • RFI schedule to be completed by

  • Precon to Ops Health Check review updated by

  • To have discussion with Site Manager on weekend working and labour model

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.