Checking items/检查信息
-
Project<br>项目名称
-
Procedure<br>工序
-
Level 楼层
-
Panel NO. 板块号
-
Checking Date 检查时间
-
Final inspection pass or fail<br>最终检查是否合格
-
QC Inspector 检查人员
Check List/检查内容
- Panel/板块
-
Panel NO. 板块编号
-
1.The material for aluminum profiles is correct<br>铝型材用料正确
-
2. Is the rubber strip used properly<br>胶条是否使用正确
-
3.The profile is clean, with no visible scratches or damage<br>型材清洁,无可视划伤/无损坏
-
4.T-profile bracket position, insertion and top spacing dimensions<br>T型挂件进出位、顶距尺寸
-
5. Is the steel saber insert core profile correctly installed on the left and right<br>钢利剑插芯型材左右是否安装正确
-
6.The protective film is applied according to the requirements<br>保护膜按要求粘贴
-
7.Fasteners are properly installed and sealed<br>紧固件安装正确/密封
-
8.The sealant is applied correctly, and excess sealant is wiped clean and neatly<br>用胶正确,余胶擦干净/整洁
-
9.Drains/vents are fabricated as per the blueprint<br>排水孔/漏气孔按图加工
-
10.Assembly height difference/corner unit angles, flatness (within 0.5mm), and step alignment meet the requirements<br>组装高低差/转角单元角度、平整度(0.5mm内)、错台符合要求
-
11.There is no significant color variation among the components<br>组件颜色无明显色差
-
dimensions of length and width<br>长宽尺寸( LENGTH/WIDTH <1m:±1.0mm;1-2m:±1.5mm;>2m:±2.0mm)
-
diagonal dimension<br>对角线 Diagonal ±2MM(<3M), ±3MM(≥3M)-需拍2张照片
-
module panel label<br>板块标签