Information

  • Site conducted

  • Form

  • Conducted On

  • Prepared By

  • Location

Production Daily Diary

  • Record Start time ( i.e 7.30 am )

  • Record Finish Time (i.e 17.30 pm)

Weather Conditions

  • Factory Conditions (Photograph the condition of the factory, storage of materials & housekeeping)

  • Record external storage conditions.

  • Live Projects Underway

  • Add photo of Whiteboard/Morning Coordination & briefing Meeting ** Detail any specific Exclusion Zones Required or change in access/egress arrangements occurring on this day**

  • Add photo of coordination meeting (whiteboard or recorded notes).

  • Planned Works in Progress and other notable events for the incoming week. **list key activities to be completed by trades and report against progress as week progresses.
  • Record module reference numbers planned for incoming week (insert photo from steel module assembly plan)

  • Record number of modules frames to be assembled on day.

  • Provide summary of the planned works completed on day.

  • Were the works for the day achieved in line with the planned schedule.

  • Reasons for works not been completed.

  • Is this delay having a knock on affect to other trades and/or the completion of the project?

  • Record the delay impact to other activities and trades.

  • Record any time delay - Hours/Days/Weeks impact on programme.

  • Record "Offline Works" planned
  • Offline works for factory build and site kit.

  • Sub-Contractor(s) on site.
  • Name Sub-contractor

  • Trade:

  • Number of operatives

  • Description of works undertaken.

  • Photo of works completed.

  • Were the planned works for the day achieved in line with the current programme.

  • Reasons for works not been completed.

  • Is this delay having a knock on affect to other trades and/or the completion of the project?

  • Record the delay impact to other activities and trades.

  • Record any time delay - Hours/Days/Weeks impact on programme.

  • Material deliveries.
  • Details of Materials delivered to site

  • Photo of docket

  • Plant deliveries or plant hire.
  • Machinery / Equipment / Plant on Hire by Procon.

  • Plant (On and Off hire Dates): Please indicate what dates (first day) that plant arrives on site and a description of what Plant is hired. Also please indicate what dates Plant is off hired from site.

  • Photo of plant inspection

  • Procon Direct Labour in the factory
  • Name of Procon Operative.

  • Visitors to site (anyone external to the Procon,excluding approved Sub-contractors)
  • Name of Site visitor (State organisation and reason)

  • Change Instructions
  • Were any instructions issued by the Procon Team?

  • Details of Instructions received.

  • Provide photo of works instructed if possible

  • Delay(s) to record.
  • Were there any delays incurred today. **This includes Sub-Contractors not completing works on Time**

  • Details of delay.

  • Detail impact of delay.

  • Number of hours delayed.

  • Detail impact of delay.

  • Number of hours delayed.

  • Detail impact of delay.

  • Number of hours delayed.

  • Detail cause of the delay.

  • Detail impact of delay.

  • Number of hours delayed.

  • Detail impact of delay.

  • Number of hours delayed.

  • Detail impact of delay.

  • Number of hours delayed.

  • Detail impact of delay.

  • Number of hours delayed.

  • Incident / Accident / Near Miss occurrence.
  • Were there any accidents or near misses to report today?

  • Has any accidents or incidents occurred?

  • Type of incident?

  • Detail Action taken; Lessons Learned.

  • Date and time of accident.

  • Description

  • Photo of area and/or any plant involved.

  • Has the Management team , incl SHEQ been informed.

  • Has the accident report been completed and issued to the SHEQ Manager.

  • Record details of incident.

  • Add photos of incident.

  • Record details for Lessons Learned

  • Have the details of the Near Miss been issued to SHEQ.

  • Has a Tool Box Talk been carried out.

  • Did the incident require medical assistance other than first aid?

  • Provide any details for ambulance or hospital requirements.

  • Any other notable incidents: e.g breach of Quality Policy, Environmental Procedures , etc.
  • Were there any safety breeches today

  • Details of incident/safety breech.

  • Date and time of incident.

  • Non Conformance issued?

STATUTORY INSPECTIONS

  • Are the statutory inspections recorded in the site Register?

  • Safety Card Observation Cards.
  • Have any Safety Card Observation Cards been issued **Procon Management encourage the issuing of SOC for lessons learned** Please use template in iAuditor .

  • Have all actions required been carried out to close any safety breech observation?

  • Record actions taken.

  • Record actions required to close and timeframe/date to close.

  • Have all actions required been carried out to close any safety breech observation?

  • Record actions taken.

  • Record actions required to close and timeframe/date to close.

  • Sign here

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.