Production Daily Diary
-
Record Start time ( i.e 7.30 am )
-
Record Finish Time (i.e 17.30 pm)
Weather Conditions
-
Factory Conditions (Photograph the condition of the factory, storage of materials & housekeeping)
-
Record external storage conditions.
-
Live Projects Underway
- DoES_07a - St Teresas
- MMCo1_Laosie accommodation unit
- DoES_43 Goatsown
- DoES_44 Scoil Muire na nBraithre
- DoES_45 St Colmcille's Girls school
-
Add photo of Whiteboard/Morning Coordination & briefing Meeting ** Detail any specific Exclusion Zones Required or change in access/egress arrangements occurring on this day**
-
Add photo of coordination meeting (whiteboard or recorded notes).
Planned Works in Progress and other notable events for the incoming week. **list key activities to be completed by trades and report against progress as week progresses.
-
Record module reference numbers planned for incoming week (insert photo from steel module assembly plan)
-
Record number of modules frames to be assembled on day.
-
Provide summary of the planned works completed on day.
- Assembly of floor steel module
- Fitting VCL to floor module
- Fitting Cemrock to floor module
- Fitting flat straps to underside of joists
- Fitting 100mm insulation to underside of floor joists (GF only)
- Assembly of roof sections
- Fitting of Topdeck
- Bolting stanchions to floor and roofbeams
-
Were the works for the day achieved in line with the planned schedule.
-
Reasons for works not been completed.
-
Is this delay having a knock on affect to other trades and/or the completion of the project?
-
Record the delay impact to other activities and trades.
-
Record any time delay - Hours/Days/Weeks impact on programme.
Record "Offline Works" planned
-
Offline works for factory build and site kit.
- Timber wall panel construction
- Glass rock for protection to posts
- Cemrock flooring
- Plywood schedule
- Fermacell schedule for wall panels
- Kingspan/Falk panels (windows and top/bottom)
- Site kit materials for closing junctions across gridlines
Sub-Contractor(s) on site.
-
Name Sub-contractor
-
Trade:
-
Number of operatives
-
Description of works undertaken.
-
Photo of works completed.
-
Were the planned works for the day achieved in line with the current programme.
-
Reasons for works not been completed.
-
Is this delay having a knock on affect to other trades and/or the completion of the project?
-
Record the delay impact to other activities and trades.
-
Record any time delay - Hours/Days/Weeks impact on programme.
Material deliveries.
-
Details of Materials delivered to site
-
Photo of docket
Plant deliveries or plant hire.
-
Machinery / Equipment / Plant on Hire by Procon.
-
Plant (On and Off hire Dates): Please indicate what dates (first day) that plant arrives on site and a description of what Plant is hired. Also please indicate what dates Plant is off hired from site.
-
Photo of plant inspection
Procon Direct Labour in the factory
-
Name of Procon Operative.
Visitors to site (anyone external to the Procon,excluding approved Sub-contractors)
-
Name of Site visitor (State organisation and reason)
Change Instructions
-
Were any instructions issued by the Procon Team?
-
Details of Instructions received.
-
Provide photo of works instructed if possible
Delay(s) to record.
-
Were there any delays incurred today. **This includes Sub-Contractors not completing works on Time**
- None to report
- Sub-Contractor Issue
- Design issue
- Procurement issue
- Supplier issue
- Manufacturing issue
- Installation issue
- Site Delivery issue
-
Details of delay.
- Client Delay
- Awaiting Design Information
- Awaiting Materials
- Sub-Contractor delay
- Delay for Crane arriving
- Delay of modules arriving as scheduled.
- Other
-
Detail impact of delay.
-
Number of hours delayed.
-
Detail impact of delay.
-
Detail impact of delay.
-
Number of hours delayed.
-
Detail cause of the delay.
-
Detail impact of delay.
-
Detail impact of delay.
-
Number of hours delayed.
-
Detail impact of delay.
-
Number of hours delayed.
-
Detail impact of delay.
-
Number of hours delayed.
Incident / Accident / Near Miss occurrence.
-
Were there any accidents or near misses to report today?
-
Has any accidents or incidents occurred?
-
Type of incident?
-
Detail Action taken; Lessons Learned.
-
Date and time of accident.
-
Description
-
Photo of area and/or any plant involved.
-
Has the Management team , incl SHEQ been informed.
-
Has the accident report been completed and issued to the SHEQ Manager.
-
Record details of incident.
-
Add photos of incident.
-
Record details for Lessons Learned
-
Have the details of the Near Miss been issued to SHEQ.
-
Has a Tool Box Talk been carried out.
-
Did the incident require medical assistance other than first aid?
-
Provide any details for ambulance or hospital requirements.
Any other notable incidents: e.g breach of Quality Policy, Environmental Procedures , etc.
-
Were there any safety breeches today
-
Details of incident/safety breech.
-
Date and time of incident.
-
Non Conformance issued?
STATUTORY INSPECTIONS
-
Are the statutory inspections recorded in the site Register?
- Plant inspections
- PUWER
- LOWER
- COSHH
Safety Card Observation Cards.
-
Have any Safety Card Observation Cards been issued **Procon Management encourage the issuing of SOC for lessons learned** Please use template in iAuditor .
- Positive Observation
- Negative Observation - At Risk!
- Potential Risk item.
- Nothing to report.
-
Have all actions required been carried out to close any safety breech observation?
-
Record actions taken.
-
Record actions required to close and timeframe/date to close.
-
Have all actions required been carried out to close any safety breech observation?
-
Record actions taken.
-
Record actions required to close and timeframe/date to close.
-
Sign here