Title Page
-
Site conducted
-
Project Name
-
Conducted On
-
Project Number
-
Location
-
Supervisor Name
-
Leading Hand
Critical Items
-
Has an environmental visual assessment been undertaken for site compound location (no potential risks from trees i.e. falling limbs).
-
Is there adequate compound access/egress (turning radius) for light to heavy plant & machinery (o/head & u/ground services, physical hazard avoidance)?
-
Is there a current copy of SHEM (latest version) onsite?
-
Is this Project Workplace Plan completed in full, authorised and dated by EC, Coord ?
-
Have services within 2.5m of excavation been located and marked?
-
Is there current DBYD (quality verified) & service location reports onsite?
-
Is there a completed Underground Services Location Checklist ?
-
Has the “Excavation Start Card” been implemented, discussed and signed with respective work crew?
-
Is there an approved TMP onsite?
-
Is there an approved TGS onsite?
-
Does the TGS reflect the actual signage layout? (Long term and daily)
-
Have relevant TMR or Council permits/ approvals (road closures etc.) been obtained for arterial roads ?
-
Has pedestrian movement been accounted for in existing TGS or as a separate TGS?
-
Is the Site Specific Induction Checklist filled out and discussed with relevant personnel?
-
Have details (online induction/ white card/ relevant tickets) and signatures of all inducted personnel been recorded on Site Induction Register ?
-
Are Site Specific SWMS filled out, discussed and signed off by relevant workers? (projects >$250k)
-
Are Minor Works SWMS completed? (projects <$250k)
-
Have Subcontractors provided copies of SWMS?
-
Is plant movement managed effectively i.e. “Plant Internal Movement Plan” been developed?
-
Is there a compliant in-date SDS folder on site?
-
Is a qualified first aid officer onsite?
-
Is there a first aid kit onsite? (1 per 25 workers)
-
Is the Daily Prestart Site Safety Meeting form filled out, discussed and signed by all workers?
-
Have all relevant environmental permits/ approvals been signed, approved and onsite. e.g. tree clearing, marine environment etc.?
-
Are all the relevant environmental controls in place (erosion and sediment control, fauna and flora ,dust, waste etc.)
-
Is signage installed and visible – PCBU signage, site office, visitors, muster point, first aid and first aiders, construction site and specific work area hazards (deep excavations etc.)?
-
Is work site demarcation and or protection set up (temp fencing, barrier mesh, bollards, barriers and correct signage installed)?
-
Is there a Lock Out/Tag Out (LOTO) Station on site noticeboard with adequate supplies of tags ?
-
Are Machinery Onboarding checklists available on site ?
Non Critical Items
-
Have COVID hygiene practices been applied? (social distancing/ hand sanitiser etc.)
-
Is there an effective safety documentation filing system onsite?
-
Has site van/compound been established ensuring approved, suitable location (e.g. private land, intersections, sharp bends, )?
-
Is a clean and working toilet (1 per 15 workers) on site?
-
Is a fire extinguisher and fire blanket on site (current tested and tagged)?
-
Is a spills kit on site?
-
Is cool drinking water available (min.2 litres per person daily)?
-
Do workers have access to generic PPE items - hard hat with brim , gloves, safety glasses, dust masks, earplugs etc.?
-
Are Sub-Contractor SWMS Review Checklists filled out and attached to each subcontractor SWMS?
-
Is the Sub-contractor SWMS register completed?
-
Does site van/ office contain relevant laminated notices/posters :-<br>CoGC WHS Commitment Policy, Emerg. procedures and contacts, Who Represents You, PPE Matrix, safety alerts, latest lifting gear test/tag month, CPR chart, latest Construction toolbox minutes and TI Safety Committee Meeting. Mins?
-
Is there a site layout (locality sketch) completed of the work site indicating first aid, fire extinguisher location, lunch room, emergency assembly point, SDS, spills kit and toilet?
Sign Off
-
Observations
-
Completed By