Header Sheet
-
Inspection Date :
-
Inspection By (Full Name) :
-
Document Number :
-
FSAM / FDA Code :
-
Inspection / Job I.D. :
-
Staff / Sub-Contractor Name :
-
Project Number (VPL use only) :
-
Field Manager Responsible :
-
Location
1. GENERAL / MANDATORY REQUIREMENTS
-
1. OH&S Risks identified and addressed.<br>
-
2. Environmental Risks Identified.
-
3. Emergency contacts known.
-
4. Dial Before You Dig (DYBD) Plans on site.
-
5. Employees inducted & competent (VPL ID).
-
6. Dedicated waste / disposal area allocated.
-
7. Environmental controls have been forwarded to the field.
-
8. Guards / Barriers / Signs positioned in correct locations.
-
9. Traffic / Pedestrian Management in place.
-
10. Traffic Management Plan completed.
-
11. Temporary reinstatement completed.<br>
-
12. Removal of Guards / Barriers / Signs.
-
13. JSA & SWMS completed.<br>
-
14. Practical Completion documents complete and accurate.
8. BUILD DROPS
8.1 Aerial - Underground Build Drop.
-
1. (ABD) MPT Mounted on Property Side of Pole, e.g. Non Climbing side or Road side.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
2. (ABD) SDS Installed to specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
3. (ABD) Correct Port used at MPT and FDH.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
4. (ABD) Minimum Clearance maintained from Power Authority Assets.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
5. (ABD) MPT labelled in accordance to labelling guideline document.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
6. (ABD) Lead-in recorded correctly on as-built.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
7. (UGBD) Premise LIC to maintain minimal coverage 300 mm.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
8. (UGBD) SDS Installed to specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
9. (UGBD) Note lead in pipe has been sealed ONLY if the pipe enters a building.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
10. (UGBD) Correct port used at MPT and FDH.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
11. (UGBD) Cable supported and housed in pit. 2-3m of slack cable at MPT to allow withdrawal.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
12. (UGBD) MPT housed in in pit in accordance with specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
13. (UGBD) LIC details recorded correctly on as-built (Telstra/NBN LIC).
-
14. (PCD) Mounted adjacent to or just above Telstra Connection Box.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
15. (PCD) Mounted vertically with latches on Right Hand Side.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
16. (PCD) Labelled in accordance to labelling guideline document.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
17. (PCD) Maintain agreed separations from Power, Gas, Water.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
18. (PCD) Cable looped into PCD correctly and terminated correctly (SDS not exposed between lead in pipe and PCD).
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
19. Site left safe, tidy, rubbish removed - Reinstatement on Private Property to be neat and tidy to meet Customer expectations.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
20. Installation meets all other design specifications and approved variations.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
21. (ABD) All fittings & terminations to specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
22. (ABD) Drop cable slack loops no less than 31cm in diameter.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
23. (ABD) Drop cable slack loops secured with cable ties.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
24. (ABD) Drop cable secured to pole as per specifications.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
25. (ABD) Attachment at Premises to specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
26. (ABD) Drop cable cleared of vegetation.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
27. (ABD) Drop cables tagged at both ends (MPT & PCD).
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
28. (ABD) All fittings & terminations to intermediate poles to specifications.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
29. (ABD) Sufficient space under eaves for bend radius of the drop fibre.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
30. (UGBD) Cable hauling to specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
31. (UGBD) Loops left in cable.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
32. (UGBD) No rope burns to cables/pits and conduits.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
33. (UGBD) Sufficient length of cable left in PCD.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
34. (UGBD) Appropriate conduit selected.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
35. (UGBD) Opti snap install as per specification.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
36. (UGBD) Duct plugs fitted to prevent ingress of foreign matter.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
37. (UGBD) 25mm gap between lead-in pipe and PCD to prevent termite etc. ingress.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
38. (PCD) Minimum 1m radial distance from any power source, including the point where the premises power supply cable connects to the property barge.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
39. (PCD) Minimum 150mm from exterior structure such as window or balcony.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
40. (PCD) Minimum 150mm from corner of wall.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
41. (PCD) Minimum 300mm allowed to open the PCD door.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
42. (PCD) Mechanical Connector terminated on drop fibre & housed correctly in PCD.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :
-
43. (PCD) Drop cables entering PCD from bottom only.
-
Defect Type :
-
Defect Location :
-
Defect Description :
-
Defect Photograph :
-
Rectification Description :
-
Rectify Defect By :