Table of Inspection or Execution Tasks
-
"Observe" shall mean to inspect these items on an intermittent basis. Operations need not be delayed pending these inspections. Frequency of observations shall be adequate to confirm that the work has been performed in accordance with the applicable documents. In the event that observations determine that the materials and/or workmanship are not in conformance with the applicable documents, additional inspections shall be performed to determine the extent of nonconformance.
"Perform" shall mean to perform these tasks prior to final acceptance for each item or element.
"Document", within the listed tasks, shall mean the inspector shall prepare reports or other appropriate written documentation indicating that the work has or has not been performed in accordance with the construction documents.
User Note: The scope of inspections contained in Appendix 1 is considered to be adequate for most installations. At the option of the Designer or AHJ, the scope of inspections may be increased for specific structures or conditions.
Table 1.1
-
Inspection or Execution Tasks Prior to Deck Placement
-
A. Verify compliance of materials (deck and all deck accessories) with construction documents, including profiles, material properties and base metal thickness <br>Req.: Perform
-
B. Document acceptance or rejection of deck and deck accessories<br>Req.: Perform
Table 1.2
-
Inspection or Execution Tasks After Deck Placement
-
A. Verify compliance of deck and all deck accessories’ installation with construction documents<br>Req.: Perform
-
B. Verify deck materials are represented by mill certifications that comply with the construction documents<br>Req.: Confirm
-
C. Document acceptance or rejection of installation of deck and deck accessories<br>Req.: Perform
Table 1.3
-
Inspection or Execution Tasks Prior to Welding
-
A. Welding procedure specifications (WPS) available<br>Req.: Observe
-
B. Manufacturer certifications for welding consumables available<br>Req.: Observe
-
C. Material identification (type/grade)<br>Req.: Observe
-
D. Check welding equipment<br>Req.: Observe
Table 1.4
-
Inspection or Execution Tasks During Welding
-
A. Use of qualified welders<br>Req.: Observe
-
B. Control and handling of welding consumables<br>Req.: Observe
-
C. Environmental conditions (wind speed, moisture, temperature)<br>Req.: Observe
-
D. WPS followed<br>Req.: Observe
Table 1.5
-
Inspection or Execution Tasks After Welding
-
A. Verify size and location of welds, including support, side-lapand perimeter welds<br>Req.: Perform
-
B. Welds meet visual acceptance criteria<br>Req.: Perform
-
C. Verify repair activities<br>Req.: Perform
-
D. Document acceptance or rejection of welds<br>Req.: Perform
Table 1.6
-
Inspection or Execution Tasks Prior to Mechanical Fastening
-
A. Manufacturer installation instructions available for mechanical fasteners<br>Req.: Observe
-
B. Proper tools available for fastener installation<br>Req.: Observe
-
C. Proper storage for mechanical fasteners<br>Req.: Observe
Table 1.7
-
Inspection or Execution Tasks During Mechanical Fastening
-
A. Fasteners are positioned as required.<br>Req.: Observe
-
B. Fasteners are installed in accordance with manufacturer’s Instructions.<br>Req.: Observe
Table 1.8
-
Inspection or Execution Tasks After Mechanical Fastening
-
A. Check spacing, type and installation of support fasteners<br>Req.: Perform
-
B. Check spacing, type and installation of side-lap fasteners<br>Req.: Perform
-
C. Check spacing, type and installation of perimeter fasteners<br>Req.: Perform
-
D. Verify repair activities<br>Req.: Perform
-
E. Document acceptance or rejection of mechanical fasteners<br>Req.: Perform
Sigjn-off
-
Inspection #:
-
Inspector Name, Signature, Date