Title Page

  • Location
  • Conducted on

  • Prepared by

Level I Verification

  • Visual Inspection of Unit for Fit and Finish of Installation

  • Take Photos from multiple angels on both load and unload side

  • Is there damage to the unit? If Yes, provide pictures of damage

  • Assign responsible person to follow up and repair/replace damaged components

Level II Verification

  • Unit(s) Placed per drawings

  • Unit(s) Leveled

  • Unit Anchoring executed as required

Utilities

  • Verify electrical connection is correct and power cord is routed properly

  • Verify Manual Disconnect

Inspect Panels, Trim and enclosure installation for completeness, fit, and finish

  • All components installed properly

  • All Panels and Trim installed

Automation

  • Unit(s) Leveled

  • Verify Alignment

  • Wheel Guides installed

  • All grounds between conveyor sections are connected

  • Ensure Foot Pedal/Remote Open Button Install and operational

Level III Verification

  • Observe operation of door(s) for smooth operation

  • Conduct Final e-stop test

Automated Units

  • Verify proper operation of automation

  • Conduct final e-stop test

  • Confirm Racks load and Unload Properly

Inspection Sign Off

  • Add any general inspection comments

  • Signature (provide First Name, Last Name, Position

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.