GENERAL
-
Builders Sign on Site and visible
-
Bin on Site
-
Toilet is clean and tidy
-
Site Safety Management Plan check
-
PPE/Safety equipment is being worn on site
IRON WORK
-
Roof colours /fascia colour as selected
-
Fascia straight and level and corner brackets fitted
-
Box gutters, parapet caps & apron flashing installed correctly
-
Valleys cut straight
-
Hip caps/caps installed correctly
-
Spin away fitted in right position as per elevation plan
-
Scribe capping (if required)
-
Down pipe correct locations and fixing/spreaders installed
-
4 stainless steel down pipe brackets for a 2 storey home into studs or timber trimmer
-
2 stainless steel down pipe brackets for a single storey home into studs or timber trimmer
-
Lining of back of parapet complete
-
Bushfire requirements met including fire walls where applicable
-
Spout to rain head sealed at wall junction
-
Boundary flashings installed
-
Photo -voltaic panels fitted
-
Rainheads installed as per plan
-
Ensure sufficient silicone used to mitred gutter curb
-
Roof fully screwed down
-
All flashing - apron flashing, maxiwall flashing installed correctly and unscratched and screwed
-
Ensure coloured rivets used to match selected colours
-
Clean gutters and roof of all debris
-
Pops to be fixed via pop river & siliconed properly
-
Manhole and roof access hatches line up
-
Check access for plasterboard delivery
-
Utilise bins wisely ie crush/fold up boxes etc
ACKNOWLEDGEMENT
-
I have read and understood the requirements of this inspection as stated in Rivergum Homes Policies and Procedures