Warehouse
-
1. Have all of the warehouse pre-build works been completed and to spec?
-
2. Has all excess warehouse equipment been removed or stored out of the way safely and securely?
-
3. Have Polypal built the new racking in the correct place and to the current spec and to the expected standard?
Works
-
4. Are all build areas clean and free from hazards?
-
5. Are barriers being used effectively to ensure the segregation of the works from work and operational areas?
-
6. Is there adequate signage higlighting the above?
-
7. Are communications being completed including? <br><br>-Daily brief to Duty manager <br>-In store communications being complpeted by Duty manager to staff using the daily brief document
-
8. Is the Daily Hazard boafd being used?
-
9. Have all contractors power tools and chargers been PAT tested?
-
10. Are all contractors on site PPE compliant?
-
11. Check fire exit and route signage compliance.
-
12. Check signing in sheets for compliance on both the contractor and store sheets?
-
13. Are there any young persons under 18 years old working on site?
-
14. If YES, has a young persons risk assessment been completed?
-
15. Is the programme on track?
-
16. Are the completed works to the current spec and to the expected high standards?
-
17. Has the SDM discussed any changes to the programme or the scope of works with the project manager?
-
18. Are welfare areas being kept clean and tidy?
Operations
-
19. Is the store trading effectively?
-
20. Is the CCTV audit compliant to the current spec?
-
21. Are the store team happy with the progress and standard of works?
-
22. Any other comments?
-
SDM
-
Site Manager
-
Duty Manager