Information
-
Document No.
-
Audit Title
-
Wates / Greenwich Peninsula
-
Conducted on
-
Prepared by
-
Greenwich Peninsula London
-
All site Team
Inspection check list
Activity: 1st fix-timber framing.
-
Check the area is clear of materials and debris.
-
All Check ceilings completed.
-
Check floor screed completed to SVP voids.
-
Check type of bathroom/ensuite.
-
Only the WC framing ( supplied by plumbing sub-contractor ) to centre line & check levels.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: fix vertical boxing.
-
Check vertical 50x50 framing to bath for plumb & level.
-
Check vertical 50x50 framing to shower for plumb & level.
-
Check low level 50x50 framing for plumb & level.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: 1st fix-12mm ply & 12.5mm tile backer board.
-
Check the fixings of both 12mm ply & 25mm backer board to faces of framing & boxing returns are below the surfaces to allow following trades to correctly fit their materials.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: fitting of laminated wall panels.
-
Checking the structural opening of the door corresponds with the drawings.
-
Check dimensions of laminated panels to fit between the ceramic tiling.
-
Fit the shadow gap materials to the face of the plaster boarded walls.
-
Check the levels of the split battens to walls & laminated panels.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining Sub Contractors responsibility until practical completion has been achieved.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor