Title Page
-
Conducted on
-
Prepared by
-
Location
-
Project
-
Client
-
Contractor
-
Site Conditions
Safety
-
Are TTM's in place and in accordance with plans?
-
Is correct PPE being used?
-
Are open trenches protected using bunting, fencing or similar?
-
Are trenches over 1.5m benched, battered or are shoring boxes in use?
-
Are materials being stored safely?
-
Are there any other safety concerns? If so detail, photograph and assign actions. Note: If there is an immediate risk to a persons safety then instruct the works to stop and contact the person in control of the site as well as Spiire Construction team.
Environmental
-
Is contractor working in accordance with the approved EPA drawings?
-
Is dust being suppressed during excavation and backfilling of trenches?
-
Are there any other concerns regarding Environmental issues? If so detail, photograph and assign actions.
Trench Excavation
-
Does trench width conform with Icon Water standards and design drawings?
-
Is there any groundwater present at base of trench? If so please detail method used for bedding and haunch and photograph.
-
Is base of trench free from rocks and loose material?
Pipe Installation
-
Does bedding material conform with Icon Water standards? If so sight site specific grading certificate.
-
Are pipes and shorts compliant with the Icon Water approved product list?
-
Is the correct jointing method being used by the contractor?
-
Are the correct revision of design drawings being followed by the contractor?
-
Are property ties installed correctly with concrete or compacted dry premix behind the junction and min/max depths inside boundary adhered to?
-
Have shorts been installed correctly with sanded piece embedded in concrete and socket/spigot facing correct way?
-
Is road sub base material approved and passing grading requirements? If so sight grading certificate.
-
Is select material free from organic material and particle sizes greater than 75mm?
-
Sewer structures
-
Is the structure as per approved drawing in relation to size and construction method?
-
Are step irons in compliance with standards and approved product list?
-
Is the neck height compliant with Icon Water standards?
-
Has correct class of lid been used as per approved drawings?
-
Has manhole been trowel finished or rubbed back to remove any dags or sharp edges?
-
Does manhole base comply with Standards and approved drawing? If offset is shown on drawing has thing been done?
Finals
-
Have compaction test been done on trench fill and do they meet compaction requirements?
-
Are sewer lines and manhole bases clean and ready for finals testing?
-
Has all Ovality testing passed? Take copy of compliance certificate for Prooving tool and ensure serial number matches.
-
Has all pressure testing passed? Take a copy of compliance certificate for pressure gauge and ensure serial number matches.
-
Has all vacuum testing passed? Take a copy of the compliance certificate for vacuum gauge and ensure serial number matches.
-
Has CCTV been done on line selected by Icon Water and are there any possible issues?
-
Have connection points been witnessed and do they line up with existing network?
-
Are any manhole lids damaged or marked with Stormwater?
-
Have gattic lids been greased and bolted down if required?
-
-
Comments