Site pre-planner
-
Job No.
-
Site Address
-
Client
-
Conducted on
-
Prepared by
-
Please include photos of any damage where required
Site Identification
-
Is address in google maps
-
Are boundary identification pegs evident<br>
-
Will site required additional site survey prior site start
-
Do any boundary fences need to be removed prior site start or during construction
-
Will retaining walls be required prior or after earthworks
-
If retaining walls are required prior site start will part install of services eg, stormwater, electrical, communications be required
Site Condition
-
Will site require slashing prior site start
-
Is site clean of all debris
-
Are there any trees that will require removal prior site start
-
Is kerb damaged
-
Is footpath damaged
-
Is there a possibility construction traffic could damage footpath
Location of services
-
Is underground power available
-
Is electrical box damaged
-
Is Telstra pit visible
-
Is Telstra pit or lid damaged
-
Is there a separate communications pit
-
Is communications pit or lid damaged
-
Is water meter box installed
-
Is water meter installed in box
-
Is water meter box, lid or meter damaged
-
Recording of current water meter usage required
-
Is natural underground gas available. check if any badges on kerbs
-
Are there stormwater kerb adapters installed
-
Is kerb type Barrier or Rollover
-
Is there a stormwater pit installed
-
Can stormwater achieve fall to kerb or stormwater connection point
-
Is stormwater pit or grate damaged
-
Is sewer manhole installed
-
Is sewer manhole pit or lid damaged
Access and storage of building materials
-
Will traffic control be required due to 100mts from a School, Hospital, Bus stop, Main rd, Traffic lights etc
-
Will deliveries stop or disrupt traffic
-
Will deliveries stop or disrupt pedestrians on footpath
-
Is there adequate parking for tradespeople
-
Is there No stopping lanes, No parking signage, No standing signs near access gates
-
Is there adequate room for storage of materials
-
Will any future building materials have to be delivered prior site start
-
Will there be additional excess soil removal from site
-
Is there an area suitable to accommodate a site shed
-
Is there an area suitable to accomodate a storage container
-
Can the site toilets be located to suit weekly servicing by supplier's pump.
-
Will extra all weather access material be required (standard 6m x 3m allowed)
-
Will extra barrier mesh be required due to fall of land, neighbouring homes at a lower level etc
-
How many gate entrances are required
-
Will additional site security perimeter fencing be required
-
Will the use of skip bins be required
-
Additional comments,