Title Page
-
Tiling inspection
-
Job No.
-
Address
-
Inspection date
-
Inspected by
-
Floor and wall tiling contractor
MAIN FLOOR AREA
-
All tiles laid true and square, no small cuts, no lipping and clean
-
Grout removed from expansion joints and in correct locations
-
Grouting complete and joints full
-
Floor tile surface cleaned of excess grout
-
Are Dishwasher space and cupboards complete.
-
Spare Full boxes only stacked neatly under stairs.
DOWNSTAIRS W/C
-
Floor tiles complete and falls to wastes.
-
Skirting tiles complete and height as per plan.
-
Grouting complete with no grout smear on tiles
-
Spare Full boxes only stacked neatly under stairs.
BATHROOM
-
Waterproofing complete and inspected prior to tiling.
-
Floor tiles complete and falls to wastes.
-
Wall tiles complete and feature tiles included in correct location and correct size.
-
Bath hob tiles completed and as per plan.
-
Skirting tiles complete and height as per plan.
-
Splash backs complete and correct to plan
-
Shower and door water stops remain and undamaged.
-
Floor waste grates installed.
-
Floor waste drains clear of tiling / bedding material
-
Grouting completed with no grout smear on tiles
-
Internal floor tile junction to Streamline angle is siliconed
-
Spare Full boxes only stacked neatly under stairs.
ENSUITE
-
Waterproofing complete and inspected prior to tiling.
-
Floor tiles complete and falls to wastes.
-
Wall tiles complete and feature tiles included in correct location to correct size.
-
Skirting tiles complete and height as per plan.
-
Splash backs complete and correct to plan
-
Shower and door water stops remain and undamaged.
-
Floor waste grates installed.
-
Floor waste clear of tiling / bedding material
-
Grouting completed with no grout smear on tiles
-
Internal floor tile junction to Streamline angle is siliconed
-
Spare Full boxes only stacked neatly under stairs.
LAUNDRY
-
Floor tiles complete.
-
Splash back over laundry tub complete as per detail.
-
Skirting tiles complete and height as per plan.
-
Floor waste grates installed.
-
Floor waste clear of tiling / bedding material
-
Grouting completed with no grout smear on tiles
-
Spare Full boxes only stacked neatly under stairs.
POWDER
-
Floor tiles complete.
-
Splash back over vanity complete as per detail.
-
Skirting tiles complete and height as per plan.
-
Grouting completed with no grout smear on tiles
-
Spare Full boxes only stacked neatly under stairs.
OTHER (if applicable)
-
Kitchen splash back complete to detail.
-
Sliding door sills complete.
-
External door sills completed
HOUSEKEEPING
-
All rubbish and packaging removed from garage and placed in bin/ cage.
-
Timber delivery pallets placed in bin provided.
-
Spare full boxes of tiles neatly stacked under stairs around corner so painter can paint wall linings.
-
House fully swept out and rubbish placed in bins provided.