Information
-
Client
-
Project Reference
-
Volsen Supervisor On Site
-
Volsen Operatives On Site
-
Roof Area
-
Conducted on
-
Prepared by
-
Location
VCL
-
VCL
-
Has the VCL been overlapped by at least 100mm?
-
Are the joins sealed?
-
Can you see that the VCL has been lapped up to the top of the insulation to all perimeters?
Insulation If Applicable
-
Insulation Type
-
Has a joining strap been fitted to the butt strap?
-
Thickness
-
How is the insulation attached to the roof?
-
Is the insulation secured to the deck properly with no bouncing boards?
Metals
-
Are the metals fixed at a maximum of 225mm centres for 1.5mm membrane, 180mm centres for 2mm membrane
-
Is there a minimum of 20mm gap between each metal joint?
-
Membrane
-
Is there a minimum of 30mm weld to the membrane laps?
-
Is there a minimum of 50mm membrane overlap?
-
Is there a minimum 30mm weld to the T-joint capillaries?
-
Do the fixing centres match the fixing schedule?
-
Are the discs fastened securely?
-
Are the discs welded correctly?
-
Is the membrane fixed/adhered properly?
-
Check dimensional accuracy of wall and course set out!
-
Set a standard of quality with sample panel, sample wall or both
-
Check all bricks delivered to site against supplied samples reject any that do not fall within the clients agreed range!
-
Bricks are to be colour selected and colour mixed as required likewise with mortar!
-
Check specifications for any special requirements ie: mortar and brick testing, special jointing, control joints and ties!
-
Brickwork minimum standard is to be as set out in the appropriate code!
-
All bricks must be laid to a string line!
-
Set all door frame heads to be a common level throughout the building!
-
Bricks must be cut off with brick saw to all face walls!
-
Check building in of door frames!
-
Check tolerances on internal walls!
-
Check installation of shelf angles and lintels!
-
Check type, location and fixing of brick ties!
-
Expansion joint locations to be checked!
-
Cavities must be cleaned by either water or chains alternatively use cavity battens!
-
Ensure that acid cleaning does not burn brickwork on completion must be left clean!
Carpet
-
Ensure substrate is prepared and cleaned prior to laying!
-
Check carpet and underlay against samples on site for conformity including colour, texture and pattern?
-
Check pattern for direction as per specification and drawings
-
Check carpet colours as per finishes schedule for colour and pattern laying per area ie: right colour, pattern per room area!
-
Check for damage or marks prior to and after laying!
-
Check joints and seams for no visible joint apparent!
-
Cross joints permitted only in low traffic areas on minimal occasions!
-
Complete installation shall be smooth and free from wrinkles, bulges, tears, creases, defective seams and stains!
-
Ensure vinyl skirting is tightly tucked between carpet and wall and glued to walls!
-
Check skirting has not been scuffed by carpet layers!
-
Check that carpet has been cleaned and floor protection installed in finished areas!
Concrete
-
Check that mpa and slump tests have been carried out and concrete as within specified tolerances!
-
Check for work and reinforcement has been inspected and approved by engineer prior to pour!
-
Check that penetrations, conduits and services are in correct locations prior to pour!
-
Check all built items and ensure correct location!
-
Check curing agent is acceptable by engineer!
-
Check that dumpy level is on site to take levels!
-
Check that samples have been taken for testing!
-
Check that records are available of where test locations are!
-
Check that all exposed edges have been tooled while concrete is workable!
-
Check all set downs and up stands are correct for future floor finishes!
-
Check all concrete finishes are within specified tolerances!
-
Check that records for pour dates, pour locations, and cure times are marked on floor plan!
-
Check that concrete is covered if poor weather conditions are apparent!
-
Clean up after each pour!
-
Check that truck wash down area is nominated!
-
Check that disposal of excess concrete is as per environmental management plan!
Demolition
-
Check that correct revision drawings and specification are onsite prior to commencement!
-
Check that services have been identified and isolated prior to commencement!
-
Check that hazardous materials survey has been obtained prior to commencement!
-
Check that engineers approval fro removal of structural elements has been obtained prior to commencement!
-
Check that slab has been scanned for services prior to cutting penetrations!
-
Check that WorkCover has been notified on intention to remove structural elements or cut structural penetrations prior to commencement!
-
Check that all items, areas or walls or clearly marked for demolition and confirmed by MPA prior to commencement!
-
Check that all adjoining properties are inspected and recorded and condition agreed prior to commencement!
-
Check that waste is segregated for recycling reuse where possible!
-
Check that all public areas are protected prior to commencement!
-
Check that all trade contractors are licensed where required!
-
Check that waste disposal summary is received weekly!
-
Check that areas are left clean and safe at end of each shift!
Electrical
-
Check that correct revision drawings and specification are available onsite
-
Check that electrical survey and installation of RCD'S, in all lighting circuits is completed prior to other trades commencing onsite!
-
Check that temporary boards clearly identify where they are supplied from!
-
Check that all temporary boards are tested for compliance and trip tested prior to using!
-
Check that temporary board circuit breakers have lockable covers with padlock!
-
Check that temporary boards display test records and are securely fastened to ground!
-
Check that electrical contractor has copies of electrical standards onsite!
-
Check that circuit identification is as per specification!
-
Check that insulating grommets are installed wherever cable pass through steel studs or purlins!
-
Check that all electrical installations are as per Australian Standards and specification!
-
Check lighting is as per specification, samples and prototypes!
-
Check that commissioning is planned and as per specification!
-
Check delivery dates for switchboards is compliant with program!
-
Check that commissioning of emergency lighting is as per AS/NZS 8293!
-
Ensure that as built drawings, manuals are submitted for review and approval as early as possible!
-
Ensure client training is given regarding operating systems!
Excavation
-
Check that correct revisions of drawings and specification are available onsite!
-
Check that all required permits and approvals are obtained prior to commencement!
-
Check that services are identified using dial before you dig or scanning prior to commencement!
-
Check and confirm locations of excavations prior to commencement!
-
Check that dilapidation report on adjoining properties is completed prior to commencement!
-
Check DA for restrictions!
-
Check levels are as required!
-
Check that shoring is installed along with safe access and protection form falling into excavation during works!
-
Check that operator for machinery are licensed and maintenance records of plant are available!
-
Check that isolation zones are installed during works as required!
Formwork
-
Check that correct revision drawings and specification are available onsite!
-
Check that Formwork is installed as per specifications, drawings, code of practice and Australian Standards!
-
Check that engineers approvals have been obtained prior to pour!
-
Check locations and levels of cast in services prior to pour!
-
Check Formwork dimensions are within tolerance, joints are tight and set out is correct as per drawings!
-
Check that all protruding reinforcement is protected against implement!
Glazing
-
Check that correct revision drawing and specification are available onsite!
-
Check that glazing method is as per specification!
-
Check glass thickness against specification!
-
Check all glazing for blemishes, cracks and imperfections!
-
Check glass for correct size, fully beaded and trade cleaned properly!
-
Check all installed glass to be properly bedded and checked for rattles or distortion!
-
Check or glazing for proper sealing of joints and glass!
-
Check that glass is cleaned correctly to avoid damage!
-
Check that glazing certificate is obtained for as installed and as per specification!
Hydraulics
-
Check that correct revisions of drawings and specification are available onsite!
-
Check locations of services prior to installation!
-
Concealed pipe work to be firmly fixed to prevent water hammer!
-
Check locations of basins, fixings and utilities prior to installation using drawing and specification!
-
Check fixtures and fitting against samples, prototypes and schedules prior to installation!
-
Check that installation is as per Australian Standards!
-
Check that underground works are documented for inclusion in as Built's!
-
Check that taps have no leaks!
-
Check that cisterns and pans are installed level!
-
Check that installed basins are water tight and level!
-
Check floor waste positions prior to installation and checked against drawings after installation
-
Check all drains are laid on firm compacted bed!
-
Check all pits are water tight!
-
Check falls on all drains are correct!
-
Check that inspection by Sydney Water is carried out when required!
-
Check that all pipe work is recorded for inclusion on as Built's!
-
Ensure that as Built's and required certification is obtained as early as possible!
Joinery
-
Check that correct revisions of drawings and specifications are available onsite!
-
Check that samples of finishes and prototypes are available onsite!
-
Check that dimensional accuracy of units is check measured onsite prior to installation!
-
Check laminate colours are as per samples and specification prior to delivery to site!
-
Check all timber to be kiln dried and strength graded!
-
Check laminate surfaces has not bubbled!
-
Check all arises have rounded edges where specified!
-
Check splash backs are the same colour where specified!
-
Check all joinery timber is free of knots, shakes, cracks or splits!
-
Check all laminates are sealed!
-
Check all joints between joinery and vanities, screens and document trays to be caulked!
-
Check all mitre, housing joints to be of good workmanship and as per specification!
-
Check all draws slide easily and have dovetail joints!
-
Check all draws and doors have equal gap spacing!
-
Check all hardware is as per specification and samples or prototypes prior to installation!
-
Check that bench tops are supported on KDHW ladder frame comprising ex 75x25 perimeter rails and ex 50 x 25!
Mechanical
-
Check that correct revisions of drawings and specification are available onsite!
-
Check that all items to be fitted of are at correct locations, heights as per drawings and specifications!
-
Check that colour of registers and units is as per specifications!
-
Check that ductwork is manufactured according to specification!
-
Check that fan guards are fitted to belts and pulleys and inlet guards fitted!
-
Check installed ductwork is dimensionally accurate, gaskets installed, corners sealed, hangers at correct intervals and damage free!
-
Check flexible ducts to have joints taped, insulated at pop cut in, firmly clamped to pops and damage free!
-
Check that all exposed pipe work is insulated with bends neatly mitred!
-
Check ductwork is clean internally and externally!
-
Check pie work is adequately clipped!
-
Check that dissimilar materials are isolated from one and another!
-
Check that insulation is applied neatly and securely!
-
Check that condensate pipe work is installed with correct falls!
-
Check there are no gaps in pipe insulation, armaflex butt joints amd longitudinal slits glued and taped!
Painting
-
Check that correct revisions of drawings and specifications are available onsite!
-
Check that sample for all finishes are available onsite!
-
Confirm correct materials upon arrival onsite prior to application!
-
Check that painting contractor has confirmed colour choices for all painting and marked on drawings prior to painting!
-
Confirm sanding of coats between coats!
-
Confirm each coat applied prior to applying next coat until all coats are applied as per specification!
-
Check all filling sanding prior to application!
-
Check filling sanding of gaps between door frame and wall lining prior to applying paint!
-
Check that stop ends are painted prior to installation!
-
Check quality of gloss finishes on pressed door frames!
-
Check if environmentally friendly substitution is possible!
-
Check all finishes have no show through!
-
Check that protection, masking tape is installed prior to painting!
-
Check that touch ups are not visible!
-
Check that shadow lines are clean and that other colours are fined cleanly!
-
Check that all protection, masking tape is removed and all marks and blemishes removed!
-
Check for paint on areas where it shouldn't be example aluminium!
-
Clean all areas painted!
Partitions
-
Check that correct revisions of drawings and specification are available onsite!
-
Check materials for conformance to specification upon arrival onsite!
-
Check walls are straight and within tolerance prior to sheeting!
-
Check location of services prior to closing walls!
-
Confirm insulation is installed and if required by client witnessed prior to closing walls!
-
Check all wall angles are mitre cut at corner and fit to a clean 45 degree angle!
-
Check all stop ends are painted prior to installation!
-
Check all joints are sanded flush with plasterboard!
-
Check that types of joints specified are achieved!
-
Check that plasterboard is installed as per manufactures specification!
-
Check there are no gaps between ceilings and walls!
-
Check ceiling grid in all directions is straight, level and true!
-
Check framework set out for ceilings incorporates linear grills!
-
Check all main runners miss all penetrations and grid system is stable!
-
Check all shadow lines are clean and level and painted!
-
Check ceiling is installed level and at correct heights!
-
Check cornice installation is straight and finished with no more gaps!
-
Check that access panels are installed at correct locations as per drawings and specification and have other trades confirmed locations!
-
Check that finishes requiring make good after other trades is completed!
-
Check the finish is acceptable prior to painting!
Reinforcement
-
Check that correct revision drawings and specification are available onsite!
-
Check and confirm all set out works!
-
Check materials comply with specification upon arrival onsite!
-
Check that specified support and cover is achieved!
-
Check trimming for all openings!
-
Check bar chairs are correctly positioned and spaced!
-
Check that plastic tipped chairs are installed on all formed faces!
-
Check that reinforcement is place in all excavated areas as soon as possible!
-
Check that plastic membrane is protected against punching from bar chairs!
-
Check that starter bars are protected to eliminate displacement!
-
When possible pre fabricate reinforcement for beams!
-
Check all reinforcement is placed as per engineers drawings!
-
Ensure that engineers sign off is obtained prior to pour!
Roofing
-
Check that correct revisions of drawings and specifications are available onsite!
-
Check all materials comply with specification upon arrival onsite!
-
Check sarking, insulation, roof sheets, fasteners!
-
Check flashings, cappings and sealants!
-
Check gutters, support brackets, downpipes, sumps and overflows!
-
Check roof lights, cowls bird proofing!
-
Check roof materials are fitted securely and made weather proof!
-
Check installation is carried out as per manufactures specifications!
-
Check adequate turn up and turn down on all sheets!
-
Check ridge capping is installed satisfactorily!
-
Check all materials abutting each other are compatible with each other!
-
Check that penetrations and flashings are designed, fabricated and sealed satisfactorily!
-
Check gutter fall and gauge!
-
Check all box gutters have overflow installed!
-
Check box sumps and dips have wire guards!
-
Check downpipes are connected to gutter or sump!
-
Check downpipes are sealed into storm water pipes!
-
Check water tightness of roof system!
-
Ensure roof is cleaned upon installation!
Vinyl
-
Check correct revisions of drawings and specifications are available onsite!
-
Check samples of vinyls to be installed are available onsite
-
Check preparation of substrate prior to installation!
-
Check and confirm colours and pattern direction and set out accordingly!
-
Check welding of seams is colour matched to agreed samples!
-
Check all joints in vinyl are straight!
-
Check jointing in vinyl to be inconspicuous!
-
Ensure that 3 mm MDF is used as floor protection for all newly completed works!