Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
TEAM
-
Add team member names here
GENERAL
-
GI Site left tidy on completion of works
-
G2 Pole planted straight and to correct depth
-
G3 Re-instatement of any holes good and excess soil removed
-
G4 Correct height of service wire achieved e.g. (5.5m @ road centre, 4.6m @ road edge, 3.0m over vehicle access.) When new POA/MCB installed by OCSC 2.7m @ 2.5m applies.
-
G5 Old hardware removed from Worksite
-
G6 Service wire installed across a boundary or pool
-
G7 Service wire installed to an accessible POA
Service / MCB Replacement
-
SV1 Bull Horn/pole/POA washer & split pin Installed for strain
-
SV2 Wedge clamps installed correctly
-
SV3 Flowline fuse/s mounted correctly
-
SV4 Correct XLPE conductor & line clamps installed and neat
-
SV5 Service wire doubled back for 6mm connection
-
SV6 Neutral tags applied to main line and service core (Total of 3 tags)
-
SV7 MCB condition compliant + shroud installed
-
SV8 Fuses / meter sealed and seals pulled tight
-
SV9 Correct vegetation clearance around service wire (min 300mm)
SITE DRAWINGS
-
Add a drawing of the site to clarify any specifics identified
-
Add a drawing of the site to clarify any specifics identified SITE DRAWINGS
SITE AUDIT SIGN OFF
-
To be signed off by the Lead Auditor conducting the Audit
-
To be signed off by the person Controlling the Workplace