Information
-
Select date
General
-
Client site: Barwon Water - Black Rock WRP 400 Black Rock road Connewarre
-
Project No: 22884
-
ITP No:
-
ITP description:
ITP/ITC Format
-
Is the ITP format consistent with Client ITP format expectation:
-
Does it show document No. (ie. ITP/ITC No.), issue number and issue date:
-
Are there separate areas for the contractor and Client representatives to sign:
-
Has a specific person/role been designated for signing off hold points and is this person on the Authorised Signature Register:
ITP Approval
-
Is the ITP/ITC approved by an authorised quality representative of the sub/contractor:
ITP Content
-
Does it address OHS / Environmental critical activities:
-
Does this ITP relate to an identifiable work element / work lot type of the WBS of the project:
-
Do all the work activities/steps listed under that work element clearly represent the complete scope of the applicable drawing and not exclude any critical items:
-
Are all the activities under that work element properly listed in a sequence: Eg. Preliminaries / work content / closeout
-
Is the work area or location mentioned on the ITP:
-
Does it incorporate Client Hold & Witness points: Are these points clearly differentiated from the contractor’s own H & W points
References
-
Does it reference specific clauses and drawing numbers rather than “as per Client specs”
Acceptance Criteria
-
Does it reflect clear and comprehensive acceptance criteria (in term of numerical values) for each activity/step as stipulated in design/drawing, technical specifications and applicable standards:
Inspection Method/Frequency
-
Is the method and frequency of testing clearly listed for each activity:
Records
-
Are the records to be kept as evidence clearly listed:
-
Does the ITP note that photos are required for buried assets and key pipeline connection points as a record:
Checklists:
-
In the Records column, does it clearly reference any checklists for repetitive items rather than having single signoff points which would not produce sufficient evidence of conformance with specifications:
Subcontractor ITP accepted
-
Does this ITP meet client requirements:
-
Any other comment :
ITP Status Inspection
-
Is Agfab inspectorate up to date:
-
Is Customer inspectorate up to date:
-
Is evidence available to verify records are up to date:
Sign off
-
Person completing the checklist
- Yes
- No
- N/A
-
Signature of the person completing the checklist
-
Select date
-
Client representative
-
Signature of client representative
-
Select date