Information

  • Client / Site Barwon Water Black Rock STP Upgrade

  • Pre Pour Concrete Checklist

  • Conducted on

Pour details

  • Please nominate reference drawings

  • Is structure a water retaining structure?

23.1 Concrete Quality

  • Concrete mix to be poured

23.2 Submission and Evidence

  • Mix design and pour methodology approved by client? HP on ITP signed?

23.3 Testing

  • Is concrete tester booked?

  • Is concrete tester NATA accredited and approved by client?

  • Slump test - (test each batch prior to placing) requirement understood by tester?

  • Sampling (Compressive test) (1 test per 25m3 per mix per day) Confirm number of tests required for pour?

  • Dry shrinkage ( Non water retaining - 1 sample every 3 months and every 200m3) (Water retaining - test first batch per pour and every 25m3 thereafter) Confirm number of shrinkage tests?

23.4 Formwork

  • If formwork requires design has design been approved by the contract administrator?

  • Formwork is positioned as per drawings? Confirm dimensions below

  • HDPE / PVC liner on forms as required by drawings and secure? Confirm with photo

  • Controlled permeability formwork liner is on critical surfaces and secure? Confirm with photo.

  • Void formers in locations as required by drawings?

  • Void formers are secure and will not deflect during placing and compacting of concrete?

  • Holes have been provided in rebate formers etc to prevent air entrapment? Confirm with photo.

  • Formwork free of water, rust, dust, debris and stains?

23.5 Cores, Fixings and Embedded Items

  • Are all cores and embedded items are in place as per the requirements of the drawings and subsequent trades? Mark on drawings.

  • Are all cores and embedded items are accurately position and firmly supported?

  • Is there reinforcement cover to all cores and embedded items?

  • For slabs, confirm that fall on slab is correct?

23.6 Placement

  • Confirm predicted ambient temperature during ? If over 38 deg in the shade do not pour.

  • Confirm predicted ambient temperature during ? If over 38 deg in the shade do not pour.

  • Confirm predicted time for discharge from list? Temperature reference is concrete temperature at time of discharge

  • Confirm temperature limit for placement of concrete?

  • Formwork temperature is less then 32 deg? Confirm with photo.

23.7 Protection and curing

  • Confirm approved curing method

  • Confirm materials and equipement for curing are onsite ready to use?

  • Confirm curing time?

23.8 Concrete finish

  • Confirm concrete finish?

  • 25mm chamfers in place for all exposed edges?

  • Confirm stripping time in days?

23.10 Joints

  • Construction joints in location as per drawings? If no have the location been approved by the contract administrator

  • Signature of Contractor Administrator if required

  • Construction joins are straight and true and free of blemishes?

  • Construction joints have been scabbled to not less the 5mm?

  • Confirm Water Stops installed as per drawings (Hydrotite CJ0725-3K on 50mm wide smooth surface)?

  • Control Joints locations confirmed?

  • Expansions joints located as per drawings? No fixed bars through joint? Joint filler installed as required?

23.11 Reinforcement Cover

  • Wet well pump station structure - Confirm that there is adequate cover to reinforcement. Select minimum cover requirement from list

  • Screen structure - Confirm that there is adequate cover to reinforcement. Select minimum cover requirement from list

24.3 Reinforcement certification and Identification

  • ACRS cert available for reinforcement used?

24.5 Standard Cogs and Hooks

  • Standard cogs and hooks supply as per AS3600? Ligs have hook of at least 135 deg?

24.6 Concrete edges

  • There is one continious bar parallel to concrete edges unless otherwise noted?

24.7 Trimmer bars

  • Trimmer bars shown on drawings in place and secured?

  • N 12 trimmer bars by 1000mm at each layer at re-entrant corners openings and penetrations not shown on drawings?

24.8 Placing and securing reinforcement

  • Reinforcement bars are the correct size and spacing as per drawings?

  • Reinforcement supported at approx 800 mm centres with approved chairs, spacers or ligatures?

  • High strength fibre reinforced spacer blocks used for all structures with exposure classification B2 Greater ( i.e. All structures except the swithroom slab)?

  • Couplers and starters located in blockouts as required?

  • Reinforcement is electrically continuous?

24.9 Placing and securing reinforcement

  • Vertical reinforcement is lapped in locations as per drawings or as approved?

  • Confirm vertical bar laps.

  • Horizontal reinforcement is lapped in locations as per drawings or as approved?

  • Confirm horizontal bar laps.

  • Confirm mesh overlaps by two wires by at least 25mm

24.11 Welding Reinforcement

  • Reinforcement not to be welded unless shown on drawings or approved by Contract Administrator. Has welding of reinforcement been approved?

  • Confirm no welds within bent sections (i.e. Within 75mm - N24, 100mm - N28 to N32, 125mm - N36)

  • Weld testing carried out i. Visual examination - 50% & Radiographic 5% fillet welds and 100% of butt welds

24.12 Cutting and bending Reinforcement

  • Has reinforcement been cut, bent or heated onsite?

  • Has approval been given by the contract adminstator to cut, bend or heat reinforcement onsite?

  • Signature of Contractor Administrator if required

24.14 Dowel Bars

  • Dowel bars are smooth and Hot Dipped Galvinised?

  • Dowel bars correct size and located as per drawings? Dowels are supported so they will not move during the pour?

25.0 Inspection completion

  • Name of the Person completing the checklist

  • Signature of the persons completing the checklist

  • Name of Barwon Water representative

  • Signature of Barwon Water representative reviewing pour

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.