General Work Environment
-
Are all work area clean and dry?
-
Rubbish/ Debris removed daily?
-
Are walkways, doorways, and exit routes kept clear and unobstructed?
-
Are toilets and washing facilities provide, kept clean, and safe?
-
Are there any hazardous materials on-site? Are they in a safe designated area? Is the SDS accessible on-site?
-
Are measures in place to protect the public from exposure to work activities and equipment?
-
Are required site induction forms readily available to all employees on-site?
-
Are monthly/ weekly "tool box" safety meetings held and documented with sign in sheets? Was a copy forwarded to the Project Manager?
-
Is material piled, stacked, or racked in a manner to prevent it from tipping, falling, collapsing, rolling, or spreading?
-
Comments:
Site Office
-
Padlock available on-site to stop unauthorised people from access?
-
Whiteboard on-site?
-
Desks and Chairs on-site?
-
Lunch Room Facilities (Microwave, Fridge) on-site?
-
Contact Details of Subbies, Suppliers, Owners on-site?
Site Appearance
-
Are site fences fixed and secured in place?
-
Are marketing signages installed on the fences?
-
Site Debris in Designated Area - Bin Located in a secured spot on-site ?
-
Site area surrounds clean and clear away of dust and debris?
-
PPE correctly worn by all site team?
-
Are materials stored in dry/ covered area?
Site Folder
-
Site folder on-site?
-
Site inductions filled out?
-
Quality assurance checklist in folder?
-
Inspection Test Points in Folder?
-
ITP's Hold Points recorder and signed by Project Manager and Builder?
-
2 Weeks look ahead program in Folder and on whiteboard?
-
Revised Construction program/ Schedule in Folder?
-
SWMS reviewed and signed by contractors?
First Aid and Emergency Equipment
-
Are emergency telephone numbers posted on the job site?
-
Are first aid kits easily accessible, inspected, and stocked at least monthly?
-
Are there any exit doors that open into streets or other high traffic areas? Are adequate warnings provided to alert employees of the hazard?
-
Kit on-site?
-
Green cross sticker installed?
-
First aid kit stocked and full?
-
Basic PPE on-site (Gloves, Masks, Safety Glasses)
-
Fire extinguisher on-site? and in service?
Fall Protection
-
Are holes and other floor openings guarded by a grate, cover, guardrail, or equivalent on all sides (except at entrances to stairways or ladders)?
-
Are there stairrails or handrails on all stairways having four or more steps?
-
Are railings provided on ramps?
-
Do all elevated surfaces have guardrails at least 1m high?
-
Where a job site has protruding steel rebar below the work level, are the steel rebar protected by covers to prevent impaled injuries?
-
Have you checked the fall guard being installed correctly secured to the building?
Portable Ladders
-
Are all ladders maintained in good condition and inspected before each use? Are broken and defective ladders taken out of service immediately?
-
Are ladders being used for their designed purpose only? (Step ladders/Extension ladders)
-
Did you make sure the ladders are not being used beyond their maximum intended load?
-
Are ladder rungs/steps slip-resistant and free of dirt, grease, oil, ice, snow, etc?
-
Are employees standing below the top 2 steps when using step ladders?
Electrical
-
Are all cord-connected, electrically-operated tools and equipment double insulated or effectively grounded?
-
Are ground-fault circuit interrupters provided on all temporary electrical circuits?
-
Are all electrical rooms/panels secured and have proper signage?
-
Do all extension cords have 3-prong plugs and all 3 prongs intact?
-
Are all electrical cords inspected and in good working condition (i.e. no splices, frays, or the ground prong is removed)?
-
Where electrical cords must cross roads, driveways, or walkways, are they protected by solid, weather-resistant bridges to prevent damage to the cords?
-
Are electrical circuits and equipment shut off, de-energized, and locked out before equipment installation, repairs, maintenance, or servicing?
-
Are unused switches, receptacles, and junction boxes covered with tight-fitting covers or plates
Trenching and Shoring
-
Are spoils, materials, and equipment set back a minimum of 4m from edge of the excavation?
-
Are barriers in place around excavation area?
-
Is high visible PPE worn by all employees working in and around trenches?
-
Are employees protected from loose rock or soil?
-
For the soil type is the excavation sloped properly?
Power-Actuated Tools / Hand and Power Tools
-
Are employees who operate power actuated tools properly trained and carry a valid operator's card?
-
Are power actuated tools inspected for obstructions or defects before use?
-
Are all tools maintained in safe condition?
-
Are damaged and defected tools removed from service and repaired or replaced as soon as the damage or defect is found?
-
Are grinders, saws, and other tools with moving parts, equipped with appropriate safety guards to prevent physical contact with moving parts?
Site Signage
-
Project Manager and Site Supervisor contact details on the signage?
-
CDC/ DA No. ?
-
Builder License Number?
-
Building Certifier Number?
-
Site Address?
-
Nearest Hospital?
-
Esteem Constructions Signage installed and visible to public?
Access and Public Protection
-
Stair Tower/ Scaffold Tagged?
-
Scaffold Tagged and Handover certificate in site folder (Weekly/ monthly)?
-
Scaffold free of materials and debris?
-
Scaffold Mesh Intact?
-
Scope/ Plans printed in Site Folder?
-
Scope/ Plans printed in Site Office?
-
Scope/ Plans printed for posting where works undertaken?
-
All details and plans are printed in A3?
-
Approved variations added to scope?
Site Plans
-
Obtain Architectural and Structural Plans?
-
DBYD service location (Call 1100)
-
Print all DBYD plans and review?
-
Obtain Sydney Water plans if required?
-
Coordinate with service providers if required?