Title Page
-
Document number
-
Site conducted
-
Conducted on
-
Prepared by
-
Lot Number
-
GIS location data from device (Phone/Tablet etc)
-
Combiner Box No.
-
General Arrangement for Corrugated Conduits from Ground
-
DC String Layout
-
String Wiring Schematics
-
Tracker Earthing Extension
-
Review the SOW, RFI register, drawing and drawing notes to ensuring the correct details have been read and understood
- Strings On Each Row
-
Number of Strings on this Row
-
Details of Strings on this Row
-
Are the corrugated Conduits Installed on to the Pile above ground from the trench as per IFC
-
Has the conduit been secured to the pile using 2 x Galvanized Bracket/ Clamp
-
Has the conduit been secured on to the Tracker using 2 x Nylon Coated Stainless Steel Cable Strap
-
Main Earth Cable installed to the First Pile of Each Row at 150mm above ground
-
Corrugated Cable Installed as per IFC between Strings, Make sure they are UV Resistant Rated
-
Install Unistrut Between Tracker Gaps to run earth using Beam Clamp as per IFC 10009-EAR-01-002.1_01.1.Tracker Earthing Arrangement
-
Earth Cables are wired through unistrut and properly connected between Trackers
-
Heat Shrinks have been properly used on cables
-
Are all cables connected correctly to the PV Module as per design
-
Capture few photos
-
All String Cables are labelled correctly
-
The +ve and -ve end of all PV Modules connected in the String are secured correctly until commissioning
-
Confirm the incoming Cable from DC Combiner Box to each String is isolated and secured until commissioning
-
Photos
Sign-off
-
All the Strings from this combiner box have been installed as per specifications
-
Supervisor or QA technician sign off
-
Complete report, email to project email address (site.engineer@jlegroup.net.au), notify JLE Project QA team to log under each Lot, all NCR or defects added to the Defects Register as required