Title Page
-
Job Name:
-
Job Number:
-
Site Location
-
Conducted on
-
Prepared by
-
Photo of plans showing ITC location
-
Pole Number
-
Has the pole location been pegged by then Surveyor?
-
Have finished levels been provided on the location pegs?
-
Has the footing been installed as per manufacturer's recommendation
-
Bore the hole for Correct Diameter
-
Correct Depth attained for the Hole
-
Stub Installed
-
Pour Concrete
-
Concrete Tested
-
Standing of Poles
-
Solar Panel with Lithium Batteries built into it have been attached to the pole
-
Light installed to the pole
-
All required connections completed
-
All joints tightened/ fixed properly
-
Lift the pole and stand it on the footing once the footing is set. Fasten the bolts
Commissioning
-
FAT Test Report
-
All Procedures followed as per Manufacturers Manual
-
Lights are Operational
-
Site Acceptance Test Completed in presence of FH
Solar Poles #
-
Attach photos of the Solar Lights/ Pole installation. (E.G. Setout, Excavation, Footing, Backfill, Installation/ Completion
-
Has the site has been left clean and safe? Barricading installed where required?
-
If areas completed hand back permit and all docs.
-
Is there any issues ?