Title Page

  • Project Name

  • Job Number

  • Inverter Number

  • Combiner Box Number

  • Combiner Box Photo

  • Date

  • Prepared by

  • Location

Combiner Box Checklist

Part 1: Initial Work Site Assessment

  • Commissioning Permit No.

  • Has the Work Crew signed and Understood the Permit

  • Has the Work Crew signed and Understood the SWMS

  • Has the Correct Commissioning Work Areas been Set up

  • Are the Correct Commissioning Lock Out and Isolation Controls In Place

PART 2

Part 2: Test Equipment

  • Insulation Tester

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • Mutli-Meter

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • Clamp Meter

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • IV Curve Meter

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • Remote Earth

  • Photo of Remote Earth

PART 3

    Part 3: Visual Inspection
  • Equipment ID

  • Confirm you are at the correct combiner box

  • Has all Labelling been Placed correctly (Capture photo from a distance to cover the whole combiner box & photo showing Labels)

  • All Fuses removed in Combiner Box & Inverter

  • All Terminations completed at Combiner Box & Inverter

  • Is the circuit breaker at combiner box open

  • Is all the string cables checked and free of any damage

  • Are all the danger tags removed

PART 4

Part 4: STRINGER PRE-ENERGIZATION ITC

  • String Visual Inspection

  • Provide Details

  • String Point to Point

  • Provide Details

  • String Cables Labelled at Both Ends

  • Provide Details

  • Attach the String Pre Energization ITC as an Appendix to end of this Document

PART 5

Part 5: STRINGER POST-ENERGIZATION ITC

  • Polarity Check

  • Provide Details

  • IR Tests

  • Provide Details

  • Open Circuit Voltage

  • Provide Details

  • IV Curve

  • Provide Details

  • Attach the String Post Energization ITC & All IV Curves as an Appendix to end of this Document

PART 6

Part 6: SUB ARRAY PRE-ENERGIZATION ITC

  • Sub Array Visual Inspection

  • Provide Details

  • Sub Array Cables Labelled at Both Ends

  • Provide Details

  • Sub Array Point to Point

  • Provide Details

  • IR Test Voltage 1000V

  • IR Test Positive to Earth

  • Provide Details

  • IR Test Negative to Earth

  • Provide Details

  • IR Test Positive to Negative

  • Provide Details

PART 7

Part 7: SUB ARRAY POST-ENERGIZATION ITC

  • Polarity Check

  • Provide Details

  • IR Test voltage 1000V

  • IR Test positive to earth

  • Provide Details

  • IR Test negative to earth

  • Provide Deatils

  • Open Circuit Voltage

  • Open Circuit Voltage

PART 8

    Part 8 - Sign Off
  • All the Test for this Switchboard/ Combiner Box Tested as per specifications

  • Supervisor Sign Off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.