Title Page
-
Client Name:
-
Job / Project Name:
-
Date Performed:
-
Technician Name:
-
Job Site Address:
-
Job Site Location:
-
Installation Condition
SOLAR (PV) INSTALL INSPECTION
-
Visually inspected each solar module
-
Cleanliness of Panels
-
Check mounting hardware is still secure
-
Check external wiring supports
-
Check the integrity of the earthing system
-
Check DC isolators for water ingress
-
Check DC isolators for correct operation
-
Check all MC4 connectors are engaged correctly
-
Check labeling is still legible and correct
INVERTER INSPECTION
-
Inverter Manufacturer
-
Inverter Model
-
Inverter Serial Number
-
Cleanliness of Inverter
-
Inverter screen is still legible
-
Check electrical wiring supports are still secure and intact
-
Check operation of DC isolators
-
Check operation of AC isolators
-
Check MC4 connectors are engaged properly
ANTI ISLANDING TEST
-
Does the inverter disconnect in less than 2 seconds with AC off
-
Does the inverter reconnect after 60 seconds with AC on
-
Does the system pass the Anti Islanding test
SYSTEM TEST
-
String Test Results
String
-
String polarity
-
String Cable Type
-
String Cable Size (mm2)
-
Irradiance at time of testing (W/m2)
-
String measured Voc (V)
-
String measured Isc (A)
-
String Vmp (V)
-
String Imp (A)
-
String Insulation Resistance Test Voltage (V)
-
String Insulation Resistance Test Pos - Earth (MΩ)
-
String Insulation Resistance Test Neg - Earth (MΩ)
-
Inverters Yearly Production Output (kWh)
-
Inverters Lifetime Output (kWh)
REPORT ANALYSIS
-
Repairs urgently needed
-
Repairs suggested
-
Overall comments on system service
-
Technician signature