Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Prior to works commencing
-
Are all drawings up to date and approved?
-
Are GL's in places provided by the main contractor?
-
Have materials been stored correctly?
-
Have installers received appropriate training?
SFS Installation
-
Does the stud pattern reflect the drawings?
-
Have the correct gages been used in accordance with the drawings?
-
Has the base and head track been installed to the correct measurement off the GL's provided?
-
Is the base and head track not overhanging the edge of the slab edge more than 1/3 of the stud width?
-
Have the studs been installed in the correct orientation?
-
Are the studs at the correct centres?
-
Have additional studs been added for brick slip/masonry joints?
-
Has the deflection gap of 25mm at the top of each stud been maintained?
-
Are cills and heads of windows installed the correct measurements? All studs above and below windows must be installed at full height
-
Are door jambs and heads installed to the correct measurements? All studs above doors must be installed at full height
-
Has jamb reinforcement at head and base track details been installed using the correct centres and measurements as per Detail no. C16/C17
-
Have high load cleat details been followed to support structure as per Detail no. C13/C14
Fixings
-
Are fixings used in accordance with the latest fixing schedule?
-
Have fixings into the studs been added on both the inside and outside faces?
-
Have fixings into the head and base track been installed next to each stud?
-
Have 5 no. fixings been installed the vertical stud to concrete column as per Detail no. A18
Sign off
-
A2O Representative Signature
-
ISG Representative Signature