Information

  • Subdivision/Stage

  • CS Number

APPLICATION & PROPERTY LOCATION DETAILS

  • Development Application No.

  • Are there any S96 amendments?

  • Current Part

  • Development Proposal

  • Address

  • Assessment Officer

  • Start Date

CONSTRUCTION CERTIFICATE PLANS

  • Construction Certificate Plans Prepared by?

  • Insert PDF Plans here

  • Notes regarding the subdivision

  • Item

COMMENCEMENT OF WORKS ON SITE

  • 1. Site Establishment

  • Pre-Construction Meeting

  • Inspection/Test results to be submitted prior to approval to proceed to next activity

  • Nominated Site Supervisor for the Project

  • List of all Sources and Suppliers of Materials submitted and approved by Council?

  • Written evidence that the Contractor has current Public Liability Insurance and Workers Compensation Insurance with Council nominated as in interested party submitted to Council?

  • Have all conditions of consent prior to the commencement of works been satisfactorily addressed?

  • Date inspected

  • 2. Commencement of Earthworks

  • Inspection/Test results to be submitted prior to approval to proceed to next activity

  • Soil and Water Management Measures installed and to satisfaction?

  • During construction conditions of consent discussed with site supervisor?

  • Select date

EARTHWORKS

  • 3. Placing of Fill on Roads and/or Lots

  • Inspection/Test results to be submitted prior to approval to proceed to next activity

  • Stripped areas inspected & to satisfaction?

  • Date inspected

ROAD CONSTRUCTION

  • 4. Road Subgrade

  • Subgrade replacement - to be approved by PCA, Granular material max 50mm aggregate

  • Road Subgrade Inspection
  • Road & Chainage details

  • Compaction Density Geotechnical test result submitted?<br>100% standard 95% modified

  • Proof roll - no sign of deflections?<br>Single axle loaded water truck or similar (min 8 tonne loaded over the rear axle)

  • Satisfactory?

  • Material that has become degraded, segregated or otherwise reduced in quality by reworking shall be rejected. Clayey and soft areas to rejected. Rejected material shall be removed, disposed of and replaced with fresh material approved by Council. Subgrade replacement - Granular material max 50mm aggregate

  • Date inspected

  • 5. Road Subbase

  • DGS 20 - 20mm nominal sized densely graded subbase
    DGS 40 - 40mm nominal sized densely graded subbase

  • Road Subbase Inspection
  • Road & Chainage details

  • Was road subgrade satisfactory/approved at this location?

  • Has a road drainage infrastructure been installed at this location?

  • Have subbase material source and type details been submitted/approved by Council?

  • Compaction density & material grading geotechnical test result submitted?<br>100% standard 95% modified

  • Proof roll - no sign of deflections?<br>Single axle loaded water truck or similar (min 8 tonne loaded over the rear axle)

  • Thickness check provided by registered surveyor?

  • Service conduit plan submitted?

  • Satisfactory?

  • Material that has become degraded, segregated or otherwise reduced in quality by reworking shall be rejected. Rejected material shall be removed, disposed of and replaced with fresh material approved by Council.

  • Date inspected

  • 6. Kerb & Gutter

  • Concrete to be minimum 20 MPA

  • Kerb & Gutter Inspection
  • Road & Chainage Details

  • Has the Subbase been approved at this location?

  • Does Subbase extend 150mm behind kerb?

  • Are kerb adapters in place and not located at contraction or expansion joints?

  • Is there adequate fall to inlet pits?<br>min 0.5% grade

  • Are contraction joints located every 3m and expansion joints at intervals not exceeding 15m?

  • Are services conduit locations adequately stamped and marked on the kerb?

  • Satisfactory?

  • Date inspected

  • 7. Base

  • DGB 20 - 20mm nominal sized densely graded base

  • Base Inspection
  • Road & Chainage Details

  • Has the Subbase been approved?

  • Have base material source and type details been submitted/approved by Council?

  • Proof roll - no sign of deflections?<br>Single axle loaded water truck or similar (min 8 tonne loaded over the rear axle)

  • Compaction density & material grading geotechnical test result submitted?<br>98% Modified

  • Thickness check provided by registered surveyor?

  • Satisfactory?

  • Material that has become degraded, segregated or otherwise reduced in quality by reworking shall be rejected. Rejected material shall be removed, disposed of and replaced with fresh material approved by Council.

  • Date inspected

  • 8. Seal - Wearing Surface

  • Check approved consent for thickness

  • Final layer Inspection
  • Road & Chainage Details

  • Has the base at this location been approved?

  • Has tack coat gone down a minimum width 300mm from kerb?

  • Satisfactory?

  • Date inspected

DRAINAGE

  • 9. Subsoil Drainage

  • Bedding - 7mm or 10mm single sized aggregate filter material 300mm of depth
    Note: in wet areas single coarse 10mm aggregate used to drain easily

  • Subsoil line Inspection
  • Subsoil Drainage Line Details

  • Subsoil drainage located on high side of all roads?

  • Is the pipe enclosed in a seamless tubular geotextile filter fabric?

  • Flush points provided?<br>At max intervals of 80m

  • Backfill trench to subgrade level?

  • Satisfactory?

  • Date inspected

  • 10. Stormwater Pipelines

  • Bedding - 7mm Quarry blend, 100mm thick, compaction 70
    Note: in wet areas single coarse 10mm aggregate used to drain easily

  • Pipeline Inspection
  • Drainage Line Details

  • Are pipelines of a satisfactory concrete cure date?<br>Pipe 450mm and less date of manufacture > 14 days<br>Pipe greater 450mm and less date of manufacture > 7 days

  • Pipeline trench widths comply?

  • Location of pipeline consistent with approved plans?

  • Adequate trench wall clearance from pipe to wall?<br>minimum 150mm

  • No poor joints, damage, unsealed lifting holes?

  • Compaction Density test results for bedding, haunch, side and overlay zones satisfactory?<br>Compacted to a density index minimum 70%.

  • Backfill to finished Subgrade level?

  • Satisfactory?

  • Date inspected

  • 10. Kerb & Gutter Drainage Inlet Pits

  • Precast pits - no honeycomb present & manufacture approved by Council

  • K&G inlet pit Inspection
  • K&G Drainage Pit location details

  • Location of pits consistent with approved plans?

  • No poor joints, damage, unsealed lifting holes?

  • Are floors rendered and self flushing?

  • Are subsurface drains present?<br>100mm diameter pipeline enclosed in seamless geotextile filter fabric extending 3m from the discharge end of pipes

  • Satisfactory?

  • Date inspected

INTER-ALLOTMENT SYSTEMS & DRAINAGE STRUCTURES

  • 14. Inter-allotment system

  • Inter-allotment Inspection
  • Inter-allotment system location details

  • Pits & pipes location in accordance with approved plans?

  • Are all pits rendered and self flushing?

  • Satisfactory?

  • Date inspected

  • 14. Place Concrete for Pits, Headwalls or Culvert Base Slabs

  • Drainage Structure Inspection
  • Drainage Structure Details

  • Reinforcing in accordance with approved plans?

  • Manufactures certification for precast products submitted & approved?

  • Satisfactory?

  • Date inspected

MISCELLANEOUS ADHOC INSPECTION

  • 15. Miscellaneous Inspection

  • Miscellaneous Inspection
  • Inspection notes

  • Add media

  • Satisfactory?

  • Enter corrective action to be taken

  • Date inspected

FINAL INSPECTION

  • 16. Final Construction Inspections

  • Construction complies with approved plans?

  • Shape and Grade in accordance with approved plans?

  • CCTV of all stormwater pipelines satisfactory?

  • Are all roads and kerb & gutter in satisfactory condition?

  • All areas levelled and stabilised?

  • All drainage infrastructure in satisfactory condition?

  • Council Infrastructure left in satisfactory condition?

  • Inter-allotment system checked to see if pipeline between each pit has not been crushed or moved?

  • Satisfactory?

  • Please issue construction compliance certificate.

  • Date inspection

DEFECTS LIABILTY

  • 17. Defects Liability periods

  • Details to be added

  • Defect Liability
  • Type of defect liability

  • Period

  • End date

  • Have you set an outlook reminder to follow up 6 weeks prior to end of period

Signature

  • Add signature

  • Date completed

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.