Title Page

  • Audit Title

  • Document No.

  • Contract

  • Total Eden

Property Outlet

  • Property Outlet Name/Number

  • Property Outlet Size (mm)

  • Property Outlet Location

  • Property Outlet Chainage

Conducted by

  • Observer

  • Conducted on

Contractor Representative

Time on Site

  • Arrive

  • Depart

Concrete Slab

  • 100mm Minimum depth compacted crushed rock bedding installed?

  • Backfill & subgrade under slab compacted to 95% MSDD?

  • Clearance around precast slab and riser pipe acceptable

  • Precast slab is free from sharp edges & no cracks evident?

Enclosure

  • Property Outlet Label installed on Enclosure?

  • Add media

  • Cage frame as per Construction drawings

  • Cage frame fabricated from Aluminium?

  • Infill panels welded to inside of Angle frame?

  • Bondor panels installed correctly and free from damage?

  • 10mm gap between bottom of gate and concrete slab?

  • Hinged doors opens freely?

  • Locking tabs installed & aligned (locks easily and on centre)?

  • Lock Installed?

  • Telemetry Aerial Installed?

  • Add media

  • Space available on slab for future mounting?

Pipes, Valves & Instrumentation

Stop/Isolation Valve to Property Outlet (Manually Operated Butterfly Valve)

  • Valve Tag Installed?

  • Add media

  • 150mm (Nominal) clearance between concrete slab and underside of flange?

  • Valve lockable?

  • Valve orientation installed correctly (no obstructions when open/closed)?

  • Valve handle faces side of enclosure that opens?

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed? (If yes specify size)

  • Other

Stop/Isolation Valve to Air Release Valve

  • Valve Tag Installed?

  • Add media

  • Valve lockable?

  • Valve orientation installed correctly (no obstructions when open/closed)?

  • Valve handle faces side of enclosure that opens?

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed? (If yes specify size)

  • Other

Pressure Guage

  • Pressure Guage Tag Installed?

  • Add media

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed? (If yes specify size)

  • Other

Inlet Strainer

  • Inlet Strainer Tag Installed?

  • Add media

  • Installed correct direction (flow arrow correct)?

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed? (If yes specify size)

  • Other

Water Meter

  • Water Meter Tag Installed?

  • Add media

  • Installed correct direction (flow arrow correct)?

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed? (If yes specify size)

  • Other

Control/Check Valve

  • Control/Check Valve Tag Installed?

  • Add media

  • Installed correct direction (flow arrow correct)?

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed on intake side? (If yes specify size)

  • Oriface plate installed on discharge side? (If yes specify size)

  • Other

Stop/Isolation Valve to Property Outlet (Lugged Butterfly Valve)

  • Valve Tag Installed?

  • Add media

  • Valve lockable?

  • Valve orientation installed correctly (no obstructions when open/closed)?

  • Clearance between enclosure and face of flange as per Construction drawings?

  • Valve handle faces side of enclosure that opens?

  • Bolts correct size/all installed and torqued?

  • Stud bolts correct length with minimum 2 thread pitches after nut?

  • Gasket installed/installed correctly?

  • Oriface plate installed? (If yes specify size)

  • Other

Pipe Supports

  • Pipe located centrally over supports?

  • Pipe adequately supported? (No signs of sagging/strain in flanges or bolts)

  • Pipe Saddle correct size for pipe?

  • Saddle around pipe installed with neoprene, rubber (or equivalent) as to not damage pipe?

Defect Items (To be added to Defect Register)

Sketches

  • Add drawing

Photos

  • Add media

Sign Off

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.