Overview
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Equipment Make, model and serial number
Testing
-
ID plate - in place, readable and ID as per project design
-
Building location, levelling alignments - Per project design
-
Building access steps or walkway - per project design, safe access assured
-
Surrounding area clean and tidy
-
Outside building good conditions - no damage that affects integrity
-
Doors, locks in good condition
-
Building equipment inside clean and in good condition
-
Metalic parts bonding and earthed
-
PV cable specs - Per project design
-
PV cable entrance correctly executed - per project design
-
Cable management good
-
Cable termination and connection - element specs as per project design
-
Allocation, polarity and labelling
-
Connection tightness and torque marking
-
Protection against direct contact in place
-
AC(LV and MV) Cable spec - per project design
-
Cable entrance correctly executed
-
Cable management ok
-
Cable termination and connection - per project design
-
Allocation, polarity and labelling ok
-
Connection tightness and Torque marking
-
Protection against direct contact in place
-
Earthing Cable spec - per project design
-
Cable entrance correctly executed
-
Cable management ok
-
Cable termination and connection ok
-
Connection tightness and torque marking
-
Cable label ok
Final assessment
-
Inspection
-
Re-inspection
-
Acceptance
-
Reservations and notes
Signatures
-
Contractor
-
Client