Does this audit include all controls from the most recent hazard and risk register?
-
Are tanks built and inspected against API standards ?
-
Add media
-
Are tanks dipped prior to discharge and verification of volume to be received completed?
-
Add media
-
Is there a High Level alarm on all tanks ?
-
Add media
-
Is there a High High Level alarm on all tanks ?
-
Add media
-
Are PV Vents in place to release internal pressure
-
Add media
-
Are competent staff used during discharge to walk tank compound checking for irregularities?
-
Add media
-
Are ignition free zones defined ?
-
Add media
-
Are floating blankets used to minimise vapour?
-
Add media
-
Are tanks electronically monitored as well as via GLI ?
-
Add media
-
Are tanks manually inspected every 30 minutes to verify tank volume
-
Add media
-
Is maximum operating pressure 7 bar ?
-
Add media
-
Is the integrity of the secondary containment verified?
-
Add media
-
Are valves in the bund closed during ship discharge
-
Add media
-
Is the ship discharge rate managed ?
-
Add media
-
Add other comments
-
Add other photos
-
List all corrective actions from this audit