Shift / Daily TTM Inspection Checklist

  • Shift inspections must be undertaken by a person holding the PWZTMP or ITCP qualification when a TGS is installed, changed or updated, to ensure the TGS is implemented as designed. This includes at a minimum, twice per shift (recommended every 2 hours). This form can also be used for inspecting 'Aftercare' arrangements.

Inspection 1

  • Start Time

Drive through TGS inspection

  • Have any adjustments been made to the approved TGS?<br>

  • If yes, provide details

  • Are changes within tolerances?<br>

  • If no, TGS must be reviewed by a PWZTMP

  • Have all signs and devices been installed in accordance with approved TGS?<br>

  • If no, provide detail of action taken

  • Are PTCD positioned as prescribed in TGS?

  • If no, provide detail of action taken

  • Are manual traffic controllers clear of travel lane, have suitable escape route?

  • If no, provide detail and reposition manual traffic controllers

  • Are sign and devices in good condition, clearly visible to road users?

  • If no, provide detail of action taken:

  • Are all signs mounted level and suitably clear of travel lanes?

  • If no, provide detail of action taken:

  • Are conflicting or non-applicable signs covered or removed?

  • If no, provide detail and remove or cover signs

  • Is temporary delineation installed as prescribed i.e. straight line forming taper?

  • If no provide details and rectify delineation

  • Have site conditions changed due to shade, park vehicles, glare etc.<br>

  • If yes provide details and note if action is required

  • Are registered trailers i.e. VMS/ light towers; suitably clear of travel lanes and delineated?

  • If no provide details and rectify location

  • Are temporary speed zones operating as prescribed?

  • If no provide details and discuss with work supervisor

  • Are workers on foot / plant clearances been applied / observed?

  • If no provide details and implement controls to rectify

Post Drive Through Confirmation

  • Is TGS valid for the site activity and operating safely as intended?

  • If no provide details and implement controls to rectify

  • Is TGS is appropriate for the current traffic conditions?

  • If no provide details and implement controls to rectify

  • Have potential hazards identified in TGS been addressed? i.e. end- of-queue management

  • If no provide details of additional hazards and controls

Sign off

  • Signed by

Inspection 2

  • Start Time

Drive through TGS inspection

  • Have any adjustments been made to the approved TGS?<br>

  • If yes, provide details

  • Are changes within tolerances?<br>

  • If no, TGS must be reviewed by a PWZTMP

  • Have all signs and devices been installed in accordance with approved TGS?<br>

  • If no, provide detail of action taken

  • Are PTCD positioned as prescribed in TGS?

  • If no, provide detail of action taken

  • Are manual traffic controllers clear of travel lane, have suitable escape route?

  • If no, provide detail and reposition manual traffic controllers

  • Are sign and devices in good condition, clearly visible to road users?

  • If no, provide detail of action taken:

  • Are all signs mounted level and suitably clear of travel lanes?

  • If no, provide detail of action taken:

  • Are conflicting or non-applicable signs covered or removed?

  • If no, provide detail and remove or cover signs

  • Is temporary delineation installed as prescribed i.e. straight line forming taper?

  • If no provide details and rectify delineation

  • Have site conditions changed due to shade, park vehicles, glare etc.<br>

  • If yes provide details and note if action is required

  • Are registered trailers i.e. VMS/ light towers; suitably clear of travel lanes and delineated?

  • If no provide details and rectify location

  • Are temporary speed zones operating as prescribed?

  • If no provide details and discuss with work supervisor

  • Are workers on foot / plant clearances been applied / observed?

  • If no provide details and implement controls to rectify

Post Drive Through Confirmation

  • Is TGS valid for the site activity and operating safely as intended?

  • If no provide details and implement controls to rectify

  • Is TGS is appropriate for the current traffic conditions?

  • If no provide details and implement controls to rectify

  • Have potential hazards identified in TGS been addressed? i.e. end- of-queue management

  • If no provide details of additional hazards and controls

Sign off

  • Signed by

Inspection 3

  • Start Time

Drive through TGS inspection

  • Have any adjustments been made to the approved TGS?<br>

  • If yes, provide details

  • Are changes within tolerances?<br>

  • If no, TGS must be reviewed by a PWZTMP

  • Have all signs and devices been installed in accordance with approved TGS?<br>

  • If no, provide detail of action taken

  • Are PTCD positioned as prescribed in TGS?

  • If no, provide detail of action taken

  • Are manual traffic controllers clear of travel lane, have suitable escape route?

  • If no, provide detail and reposition manual traffic controllers

  • Are sign and devices in good condition, clearly visible to road users?

  • If no, provide detail of action taken:

  • Are all signs mounted level and suitably clear of travel lanes?

  • If no, provide detail of action taken:

  • Are conflicting or non-applicable signs covered or removed?

  • If no, provide detail and remove or cover signs

  • Is temporary delineation installed as prescribed i.e. straight line forming taper?

  • If no provide details and rectify delineation

  • Have site conditions changed due to shade, park vehicles, glare etc.<br>

  • If yes provide details and note if action is required

  • Are registered trailers i.e. VMS/ light towers; suitably clear of travel lanes and delineated?

  • If no provide details and rectify location

  • Are temporary speed zones operating as prescribed?

  • If no provide details and discuss with work supervisor

  • Are workers on foot / plant clearances been applied / observed?

  • If no provide details and implement controls to rectify

Post Drive Through Confirmation

  • Is TGS valid for the site activity and operating safely as intended?

  • If no provide details and implement controls to rectify

  • Is TGS is appropriate for the current traffic conditions?

  • If no provide details and implement controls to rectify

  • Have potential hazards identified in TGS been addressed? i.e. end- of-queue management

  • If no provide details of additional hazards and controls

Sign off

  • Signed by

Inspection 4

  • Start Time

Drive through TGS inspection

  • Have any adjustments been made to the approved TGS?<br>

  • If yes, provide details

  • Are changes within tolerances?<br>

  • If no, TGS must be reviewed by a PWZTMP

  • Have all signs and devices been installed in accordance with approved TGS?<br>

  • If no, provide detail of action taken

  • Are PTCD positioned as prescribed in TGS?

  • If no, provide detail of action taken

  • Are manual traffic controllers clear of travel lane, have suitable escape route?

  • If no, provide detail and reposition manual traffic controllers

  • Are sign and devices in good condition, clearly visible to road users?

  • If no, provide detail of action taken:

  • Are all signs mounted level and suitably clear of travel lanes?

  • If no, provide detail of action taken:

  • Are conflicting or non-applicable signs covered or removed?

  • If no, provide detail and remove or cover signs

  • Is temporary delineation installed as prescribed i.e. straight line forming taper?

  • If no provide details and rectify delineation

  • Have site conditions changed due to shade, park vehicles, glare etc.<br>

  • If yes provide details and note if action is required

  • Are registered trailers i.e. VMS/ light towers; suitably clear of travel lanes and delineated?

  • If no provide details and rectify location

  • Are temporary speed zones operating as prescribed?

  • If no provide details and discuss with work supervisor

  • Are workers on foot / plant clearances been applied / observed?

  • If no provide details and implement controls to rectify

Post Drive Through Confirmation

  • Is TGS valid for the site activity and operating safely as intended?

  • If no provide details and implement controls to rectify

  • Is TGS is appropriate for the current traffic conditions?

  • If no provide details and implement controls to rectify

  • Have potential hazards identified in TGS been addressed? i.e. end- of-queue management

  • If no provide details of additional hazards and controls

Sign off

  • Signed by

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.