Air blown fibre microduct system sealing - NDF-13042
-
FFP ID (Exchange/FFP)
Site details
-
A-FFP ID
-
Add location
-
Visionstream
-
Select date
-
Contractor company
-
Contractor name
-
Mobile number
-
Signature
Verifiction details
-
All 'end of run' installations must be recorded
-
Add location
-
Duct number (eg D1)
-
Photo evidence (microduct capping)
-
Photo evidence (microduct closure)
-
Add location
-
Duct number (eg D1)
-
Photo evidence (microduct capping)
-
Photo evidence (microduct closure)
-
Add location
-
Duct number (eg D1)
-
Photo evidence (microduct capping)
-
Photo evidence (microduct closure)
-
Add location
-
Duct number (eg D1)
-
Photo evidence (microduct capping)
-
Photo evidence (microduct closure)
-
Add location
-
Duct number (eg D1)
-
Photo evidence (microduct capping)
-
Photo evidence (microduct closure)
-
At the completion of the Microduct system build and before handover to Chorus, please confirm the following information is a true and correct representation of the completed work
-
Microduct is trimmed to 80mm height from the base of the flash 9
-
All microducts labelled
-
Complete the microduct test procedure as per the document - Integrity Testing of Microduct System (ND0558 & Test verification NDF-215
-
All in use 5mm microducts sealed with strain relief plugs (tails down)
-
Microducts 53 and 54 end capped with correct red end cap
-
All spare 5mm and 12mm microducts end capped with correct red end cap
-
Microduct jointing completed, wrapped and managed within pit
-
Microduct system jointing to all customer one way microducts correctly installed and jointed
-
All one way microducts at customer boundaries end capped, heat shrunk and labelled
-
All end of run microduct systems end capped and closure fitted
-
Pit lid secured with plastic bolts
-
Pit lid insert covers in place