Information

  • FFP

  • Conducted on

  • Site Manager

Civil Works

  • Has at least 1 Progress QA been completed on the Civil Works for this site?

  • Have all Progress NCRs been rectified?

  • Has all Ribbonet Jointing been completed/tested/buried

  • If no to any of the questions above, please complete prior to continuing with this form and requesting a final audit.

Fibre Works

  • Has all fibre work - both aerial and underground been completed?

  • Has the Exchange work been completed?

  • Have all splitters been spliced in?

  • If no to any of the questions above, please complete prior to continuing with this form and requesting a final audit.

Documentation

  • Are Civil and Fibre Asbuilts available in Viscore?

  • Are NDF245 and NDF13042 available in Viscore

  • Is the Pole to Boundary Data Sheet available in Viscore?

  • If no to any of the questions above, please complete prior to continuing with this form and requesting a final audit.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.