Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Pre Work Inspection ( to be completed prior to beginning work)
-
Purchase order has been received.
-
There is no damage to tubs, showers, countertops, stairs, windows, vinyl, etc.
-
All Protective coverings are in place (tubs, countertops, vinyl, etc.)
-
All drywall repairs have been completed, surface is smooth and sanded with no raised face paper from over sanding.
-
All damaged trim has been repaired or replaced.
-
Unit is ready to be painted.
-
Unit is clean, broom swept, and free of debris.
-
Trade Contractor: Company Name (printed)
Final inspection: ( to be completed before Trade Contractor leaves job site)
-
Site Superintendent:
-
Second coat of paint applied to walls is smooth, with no runs, drips, lumps, color variations, streaking, or light spots using ProMar 200 latex wall paint Eggshell Finish.
-
Second coat of trim paint applied to walls is smooth, with no runs, drips lumps, color variations, streaking, or light spots using ProMar 200 Latex wall paint Eggshell Finish.
Summary
-
Date: Project superintendent:
-
Trade Contractor: Company Name:
-
Project manager
-
Second coat of trim paint applied to trim the doors are smooth, with no runs, drips, lumps, color variations, streaking and all the doors are painted on ALL SIDES tops and bottoms using ProMar 200 Alkyd semi gloss enamel.
-
All metal handrails and guard rails are painted per plan.
-
There is no damage to drywall, stairs, handrails, trim, etc..
-
Paint spills have been removed without damage to vinyl, wood floors, tubs, showers, countertops, etc..
-
Paint has been removed from window glass and aluminum trim.
-
Paint has been removed from door hinges and all hardware.
-
Doors have been re-hung, and are square, level, plumb, and back where they belong.
-
No defects are visible under sunlight and normal house lighting from a distance of 6 feet for the entire interior paint job.
-
There is no paint residue in sinks.
-
Debris has been removed to the dumpster.
-
Unit is clean and broom swept.
-
Excess material is stored in designated areas.