Title Page
-
Weekly Safety Audit
-
Jobsite Location:
-
Job Name:
-
Date of Inspection:
-
Weather
-
Project Superintendent(s)
-
Audit Performed By:
GENERAL SAFETY & HEALTH
-
Government / All-In-One Posters Up to Date (English & Spanish)
-
Safety Meetings / Pre-Task / Equipment Inspections Up to Date
-
Stretch & Flex Completed
-
SDS Current / Binder Available
-
Chemical Contents Clearly Labeled as to Contents / Form Oil / Diesel / Gasoline / Curing Compound
-
Muster / Rally Point Identified & Communicated to Workers
-
OSHA 300 Summary Posted Feb 01 - May 01
-
Green Tape affixed to New Hire Hard Hat
-
UFI Site Specific Orientation completed
FIRST AID
-
First Aid Kit Readily Available and Stocked Properly
-
First Aid / CPR Personnel - Training Current / 2 Person Minimum
-
Place Designated for Cooling Off
SITE / PUBLIC PROTECTION
-
Ground Level Barricades / Signs / Cones / Cone Poles in Place Where Needed
-
Orange Netting in Place / Active Deck
-
Orange Netting in Place / Permanent Guardrail
-
Traffic Control / Training / Stop Slow Paddle / Hi-Viz Garments
-
Diesel Tank Double Wall with Berm / Barricaded / No Smoking Sign / Bonding Strap
PERSONAL PROTECTIVE EQUIPMENT - INCLUDING SUBCONTRACTORS
-
Hearing Program Followed Where Required / Pans / Grinding / Chipping /
-
Functional and in Good Repair. Employees Wearing Appropriately / Glasses / Hard Hats
-
Dark Glasses not being used Inside Building
-
Respiratory Protection Program Followed Where Required (water, vacuum, OSHA Table 1)
-
Fall Protection - Full Body Harnesses
-
Fall Protection - Retractable Lifelines
-
Hand Protection - Task Specific
-
Face Protection - Task Specific
-
Foot Protection (Sturdy work boots, cover heal)
-
Proper Clothing, Hi-Viz Vests or Shirt
-
Eye-Wash Station Available During Concrete Pour
CONCRETE CONSTRUCTION
-
Post Tension Cable Pulling Operations Protected with Barricades & Signs
-
Impalement Protection / Rebar Caps
HOUSEKEEPING
-
Work Space Clean & Free From Excess Trash / Nails / Debris from Cutting Wood / Banding
-
Materials Stored and Stacked on Firm Foundation at Least 10 Feet from Edge of Slab
-
Garbage can available outside office / emptied at regulars intervals?
-
Water Kegs / Sanitary / Cups / Trash Receptacle
-
Task Lighting / Daylight / Night Time Pours Walkways & Ladders
LADDERS & STAIRWAYS
-
Extension Ladder / Secured / Orange Walk-Thru Hand Grab Bars
-
A-Frame Ladders / Used Correctly / Decals in Place
-
More Than One Ladder for 25 or People on any Level
-
Ladder Used to Access Dumpsters / Flatbed Trucks / Etc
-
Stairways Equipped with Handrails Installed Between 30-37"
-
Job Made Ladders / Pull Up Rope / Steal Grab Bars
-
Job Made Ladder Rungs 12" on Center & Side Rails 16"-20" Apart Properly Constructed
-
Ladders Side Rail Extends 36" - 42" Above Landing Area and Secured
-
Stair landings lighted with clear and clean access?
FALL PROTECTION
-
Adequate Temporary Guardrails Installed Properly
-
Adequate Permanent Guardrails Installed Properly / Wood & Cable
-
Stairs / Ramps / Walkways
-
Elevator Shafts Protected
-
Fall Protection - Permanent Column Safety Straps
-
Holes 2 Inches or Wider Covered / Secured / Labeled
-
Hand Rails Installed Properly up to Leading Edge Barricades
-
Horizontal Lifelines Installed Properly
SIGNS, SIGNALS & BARRICADES
-
Stripping Signs Posted with area Barricaded
-
Fall Hazard Areas Barricaded Properly with Signage
-
Lower Level Controlled Access Zone Set up Properly During Stripping Process
TOOLS & EQUIPMENT
-
Broken Tools Removed from Service / Tagged Out
-
Hand Tools Observed in Good Shape
-
Air Compressor Have a Shut Off Valve on Blow Pipe
-
Air Compressor Hose Conditon
-
Extension Cords / Power Tool Cords / Knicks / Ground Pin
-
Hammer Head in Good Shape with no Grinder Cuts
-
Side Handles Being Used on Grinders and Drills
-
Saw Horse in Use / Top Plate Inspected / Saw Blade Adjustment
-
Safety Retainers on Air Compressor Hoses to Prevent Accidental Disconnect
SHORES, RESHORES, STRIPPING & STRIPPING NETS
-
Perimeter Lacing Installed on all Unsecured Shores to Prevent Accidentally Falling Out of Place
-
Stripping Nets in Good Shape / On Site (order when framing material is shipped)
-
Shoring Scaffolding with a Height to Base Ratio Greater than 4 to 1 is Restrained from Tipping by Guy Wires, Bracing or Equivalent Means
-
OSHA Planks Used were Applicable
FIRE PROTECTION
-
Generator(s) - 10# Fire Extinguisher Mounted on Stand with Red Flag / Certification Current
-
Plywood placed under generator while being using on ground level (keeps oil from going into dirt)
-
Diesel Tank - 20# Fire Extinguisher Mounted on Stand with Red Flag / Certification Current / 25 to 75 Feet Range
-
Chopsaw or Torch - 10# Fire Extinguisher Mounted on Stand with Red Flag / Certification Current
-
Torch Set / Gauges / Flash Back Arrestors / Hose Condition / Storage of Tanks
-
Flammable Storage Tank
SCAFFOLDS
-
Leveled / Footing
-
Pins / Laced Properly
-
Planks / Platforms
-
Guardrails / Employees Tied Off
-
Swingstage Cables / Tie Backs
-
Life-lines / Rope Grabs
EXCAVATIONS
-
Spoil Piles at Least 2 Feet Minimum From Excavation
-
Proper Entry & Exit in Place
-
Properly Barricaded
-
Employee Training Completed / Pre-Task Plan Completed
-
Ladder Provided if Deeper than 4 Feet
CRANE, RIGGING & LIFTING EQUIPMENT
-
Chain Sling condition (tag in place and legible, hooks)?
-
Tag Lines of Proper Length for Specific Tasks
-
Concrete Column Bucket (wire rope, tag legible, shackle cotter pin)
-
Port-A-John with Proper Rigging Being Utilized
-
Crane Swing Radius Barricades in Place
-
Heavy Equipment Daily Inspections Completed
-
20-Foot Straps condition (red yarn, legible ID Tag)?
-
Skip Pan / Wire Rope / Shackles / Weight Stencil
-
Crane Radius Plan Available
OUTRIGGER
-
Guardrail systems are in place and at proper height?
-
Plywood installed on sides - top to bottom
-
Double 2x4 stop block in place and secured at the end of outrigger?
-
Tie off anchors identified and in place?
-
Orange cones and plastic cone bars in place around outrigger? 10 cones 9 cone bars
-
Shackles screw pin type with the pin fixed from rotation by either a cotter pin or ‘mousing’ with tie wire?
-
Fall protection required beyond this point in place at entry?
-
Blue Notice Sign 5,000 Pound cart load in place?
-
Guardrails put back in place where the outrigger was removed from?