Title Page
General Information
-
Project:
-
Contractor:
-
Conducted on:
-
Location:
-
Completed By:
-
Record Number:
Compliance Questions
1. Documents
-
1.1: Is the approved Welding Procedure Specification (WPS) available on-site and compliant with the project specification?
-
1.2: Is the WPS in English and qualified by a Procedure Qualification Record (PQR) as required by the specification?
-
Verify the qualification of the WPS with the relevant PQR documentation. Ensure the PQR is endorsed by a recognized third party
-
1.3: Are current WPS documents controlled to prevent the use of outdated or unapproved revisions?
-
Describe the system in place for controlling WPS documents
-
1.4: Are welder qualification records demonstrating ASME IX compliance available and endorsed by a recognized third party
-
Show endorsements by a recognized third party.
-
1.5: Are welders assigned unique IDs and identifiable on-site with name and photo badges?
-
Provide a photo of the ID card
-
1.6: Are welder continuity logs maintained, ensuring qualification remains valid (six-month)?
-
Provide a sample of welder continuity logs
2. In-Process Welding
-
2.1: Are welding inspectors certification up-to-date to ensure competent inspection of welding activities?
-
Select Qualification
- CSWIP
- AWS/CWI
- PCN
- Other
-
2.2: Do welding activities comply with the parameters outlined in the approved WPS?
-
Conduct a parameter check and record the result
-
2.3: Are preheat and interpass temperatures monitored and controlled as per WPS?
-
2.4: Is there a process to verify the base materials match the specification in the WPS?
-
2.5: Are filler materials controlled and verified to comply with the WPS requirements?
-
2.6: Are baked SMAW electrodes held in a quiver at the workplace at a minimum of 70°C?
-
2.7: Does the quiver have a valid calibration certificate?
-
2.8: Before welding, is the weld bevel visually inspected for mechanical damage or corrosion?
-
2.9: Are tack welds compliant with the WPS, made by qualified welders, and checked for proper length (at least 25mm) and condition?
-
2.10: Is inter-run cleaning performed with the correct material tooling?
-
2.11: Is the welding environment adequately protected from draughts and inclement weather?
-
Provide photos or descriptions of environmental controls in place.
-
2.12: Is the backing gas used as per the qualified WPS?
-
2.13: Has the purge monitor been correctly deployed?
-
2.14: Are shielding/backing gases used in the correct mixture and ratio as specified?
-
2.15: Are weld joint identification numbers marked near the weld?
3. Post Welding
-
3.1: Has a visual inspection been performed on the weld according to the specified standard?
-
Select the Design Code
- ASME B31.3
- API 1104
- AWS D1.1
- Other
-
3.2: Are inspectors performing visual inspections familiar with the specified acceptance criteria?
-
3.3: Does the weld profile meet the criteria, including no excessive convexity, concavity, or undercut?
-
Provide the weld joint ID
-
3.4: Are the size and length of the fillet welds verified to meet the design specification?
-
3.5: Is the alignment and distortion of the welded joints checked?
-
3.6: Are the necessary NDE methods (RT, MT, PT, UT) performed as specified
-
Select the Method
- Radiography
- Manual Ultrasonics
- Automatic Ultrasonics
- Phased Array
- Magnetic Particle
- Dye Penetrant
-
3.7: If defects were identified during NDE, have they been documented and addressed per project-specific?
-
3.8: Has a final NDE report been generated from the inspections?
-
Provide NDE inspection report
Feedback
-
Is there any way to improve our online form? Please enter the information below.