Title Page
-
Location of works
-
Conducted on
-
Work Start Date
-
Permit Expires
-
Prepared by
-
Description of work
-
Unique Ref No (if available):
-
Name of Team Leader
-
Names of all team members (if any)
Pre-Work Checklist
Site Protocols
-
All members of the contractor team have signed in
-
All contractors are visibly wearing their pass?
-
Contractors made aware of toilet locations?
-
Contractors advised of fire exits?
-
Contractors advised of fire assembly point?
-
All contractors wearing safety shoes
-
Has product and work areas been protected against contamination and damage?
-
Contractor knows how to reach their site contact
Permit Type
-
Dynamic - urgent/routine works to be conducted under Trident generic RA and Supervision
-
If no, escalate to the Health & Safety Team to complete the remainder of the form
-
Have the contractors been provided with a copy of PC1-7 - Safety Regulations for Contractors
-
Request a copy. Now received?
-
Is there a method statement covering the full scope of works?
-
Do the contractors have a copy with them?
-
Do we have a copy on file?
-
Is there a Risk Assessment covering the full scope of works?
-
Do the contractors have access to a copy?
-
Do we have a copy on file?
-
Do we have a copy of liability insurance certificates?
-
Is it possible to implement the controls proposed on the RAMs?
-
Designated walkways and emergency exits will be kept clear at all times unless working on them (then barriers must be deployed)
-
Has the work area been inspected prior to works?
-
Area clear of unexpected hazards or obstructions?
-
Can the hazards be removed or controlled adequately to allow the works to proceed?
-
Can additional and adequate controls be implemented?
-
Are works now safe to proceed?
-
Door access card issued?
Personnel
-
Contractors aware of accident reporting process?
-
Do any of the team have a medical condition which may affect them while on Trident premises?
-
Are any of the contractors first aid trained?
-
Do contractors know what action to take in the event of an accident?
-
Do the contractors have their own first aid supplies?
-
Does the contractor's First Aider know the location of our supplies?
-
Is their first aider aware of our accident reporting process?
-
Contractors aware of how to contact a first aider?
-
Are the team members qualified for the work to be undertaken?
-
Does the team leader know how to reach his Trident contact?
-
Do all team members feel safe with the current controls?
-
If carrying out lifting activities, is the load within contractor's capabilities?
Equipment
-
All electrical equipment is PAT tested
-
Are any chemical substances to be used?
-
Are Safety data Sheets available for all chemicals to be used?
-
Is the correct tooling and equipment available to carry out the work as per RAMS?
-
Is the equipment free from defects?
-
Is correct signage and/or barriers available?
-
Is the correct PPE available as stated in the RAMS?
-
Is any mechanical lifting to be used as part of the task?
-
Is operator qualified?
-
Photo of qualification
-
Has all equipment been inspected?
-
Harnesses will be worn
-
Is any heavy lifting involved in this task?
-
Are all staff involved in lifting trained in manual handling?
Confined Spaces
-
Does this task involve entry to confined spaces?
-
Is this satisfactorily covered in the RAMS?
Electrical
-
Does this work involve working on or near electrical systems?
-
Is this satisfactorily covered in the RAMS?
-
Can the power be isolated with a secondary isolation?
-
Can a safe isolation lock be applied?
-
How will the contractor guard against accidental switch on?
Hot Work
-
Does the task involve any hot work?
-
Has a hot work permit been issued?
Working at Height
-
Does this work involve working at height?
-
Is this satisfactorily covered in the RAMS?
-
Have all ladders and/or other equipment been inspected?
-
Are ladders of fiberglass construction
-
Contractors provided with Fiberglass ladders
-
All ladders labelled as compliant to BS EN 131?
Environmental
-
Are contractors aware of the environmental impact reporting policy?
-
Are contractors aware of spill kit locations?
-
Will any of the activities produce high noise levels?
-
Is this likely do disturb neighbours?
-
Will works be complete by 18:00?
-
Has adequate provision been made to deal with any waste materials?
-
List expected waste streams?
-
Any waste to be considered hazardous?
-
Are adequate provisions in place to deal with hazardous waste (appropriate containers, safe storage areas).
-
Are current or expected weather conditions likely to increase the risk?
-
Are safe working limits agreed (work will stop when limits reached)?
-
Details of anticipated risk:
-
Is visibility, light level or ground condition likely to increase risk?
-
Are other activities in the area likely to increase the risk?
-
Details of anticipated risks:
-
Are safe working limits agreed (work will stop when limits reached)?
-
Is mitigation in place to address this?
Site Access Pass
-
Pass card issued
-
Access Level
-
Justification for access all areas
-
Acknowledge access cards will be returned to issuer
-
Understand that lost passes must be reported immediately
Setup of working area
-
Inspect work area(s) to assess for unexpected hazards or circumstances?
-
Can the area be made safe prior to commencement of work?
-
Are additional precautions required?
-
Appropriate warning signage displayed?
-
Barriers deployed?
-
Are Trident staff in the area aware of the work and potential hazards?
Completion of Task
-
Site contact will be briefed on progress prior to leaving
-
All work areas will be inspected at the end of each day to ensure tidy and free from hazards
-
Visitor ID to be returned to box in reception
Permission To Start
-
Contractor representative confirms that all information provided is accurate and that all team members under their control are aware that all work must be carried out in compliance with the RAMS and Trident site rules. Work will cease immediately if any changes occur which are not covered by the RAMS or this assessment and may not continue until a reassessment is made.
-
Name and signature of contractor team leader
-
Permission to work is granted with the defined controls.
-
Trident Representative name & signature
-
Contractor may now start job as planned. Complete finial section "Permit Closure" on completion of works.
Additional Information (optional)
-
Feedback/Comments/Amendments?
Permit Closure
-
Site contact briefed on progress prior to leaving site
-
Works completed as agreed to satisfactory standard
-
Door Access pass returned/cancelled
-
Work area left in safe condition
-
Comments:
-
Date/time closed
-
Work accepted and Permit closed by
-