Title Page
-
Site conducted
-
Conducted on
-
Commissioned by
-
Location
COMMISSIONING PREREQUISITES:
-
Coordinate site access to the array, inverters, AC and communications equipment.
-
Verify SolarEdge user access to SetApp and the site in SolarEdge monitoring portal.
-
Verify DC strings properly terminated.
-
Verify and record all string polarity and correct safety voltages.
-
Verify AC conductors properly terminated.
-
Verify AC grid voltages within range (measured at the inverters).
-
All SolarEdge equipment mounted per specifications.
-
Verify communications are established with the SolarEdge monitoring portal.
SITE MAPPING:
-
SolarEdge monitoring portal Site ID:
-
Inverter (and SolarEdge Gateways if present) placard number is consistent with monitoring portal IDs.
-
Monitoring portal’s physical layout reflects as-built conditions.
-
Power optimizer serial numbers scanned to module locations (Use SolarEdge SiteMapper app).
-
Power optimizer stringing completed in the monitoring portal (as built conditions).
INVERTER INSTALLATION CHECKLIST:
-
Inverters are mounted in accordance with installation manual.
-
Inverter AC voltages are verified to be within range prior to energizing the inverters.
-
Firmware is upgrade via SetApp (verify and record same DSP version on all inverter units)
-
Country code configuration verified.
-
Special grid requirement configuration verified (if applicable). (Special grid requirements if applicable).
-
All power optimizers paired.
-
All inverters achieve expected production.
THREE PHASE INVERTER WITH SYNERGY TECHNOLOGY INSTALLATION CHECKLIST (IF APPLICABLE):
-
Is the installed inverter a Three Phase with Synergy Tech
-
AC Terminations are properly completed in accordance with inverter manual.
-
Tongue Lugs are crimped in accordance with lug manufacturer specifications
-
Lugs are compatible with AC conductors and inverter terminals.
-
Lugs are insulated with properly rated heat-shrink or equivalent.
-
Verify all connections to Synergy units are properly connected and safety rings are installed.
-
Verify in SetApp all Synergy unit serial numbers and expected production.
COMMUNICATION CHECKLIST:
-
Leader device connected to the SolarEdge server and displays “S_OK”
-
RS485 properly wired. (Strongly recommend shielded three conductor twisted pair plus a drain)
-
All follower inverters detected (if applicable).
-
If a third-party communications setup is being used.
-
Verify Modbus ID for each SolarEdge device is set correctly.
-
Verify baud rate is the same between platforms.
-
Sensors (if installed) are reporting expected values.
-
Modbus energy meters (if installed) are reporting expected values.
POWER OPTIMIZER INSTALLATION & DC WIRING:
-
Inverter Installation Checklist:
-
Power optimizers bonded/grounded properly to the mounting structure
-
Spot check for correct PV connections at the module, between arrays and in home runs:
-
All mated connectors are compatible.
-
Field-made MC4 connections are installed correctly
-
All jumpers and adaptors meet SolarEdge guidelines
-
Adequate wire management to ensure long term system integrity & safety. (free from water intrusion, pests, abrasion, or other hazards)
-
DC strings terminated at inverter in accordance with installation manual:
-
Verify and record all String Polarity and correct Safety Voltages (free air test–not landed on inverter terminals)
String Voltages
- String #
-
String #
-
VDC + to G
-
VDC - to G
-
VDC + to -
Inverter Measurements
- Inverter #
-
Inverter #
-
Inverter Serial #
-
kW rating
-
Vac L1 to L2
-
Vac L1 to L3
-
Vac L2 to L3
-
Vac L1 to G
-
Vac L2 to G
-
Vac L3 to G
-
Vac N to G
-
Synergy Unit (if applicable)
-
Power AC (each unit)
-
Pac Measurements L(C/R)
Voltage DC (each unit)
-
VDC Measurements (L/C/R)
Notes
-
Notes