VISUAL CHECKLIST

  • Marine grade aluminium (10 gauge)

  • 316 stainless steel 1.5mm thickeness

  • Enclosure rating minimum IP56

  • Shade hood fitted

  • LCS support frame is fabricated from hot dipped galvanised steel and affords suitable support and rigidity, JBox not damaged

  • LCS enclosure securely mounted with galvanised bolts, nuts and washers

  • Hot dipped galvanised clamps used to mount to structural steel<br><br>Note * Drilling or welding of structural steel Is not permitted

  • All dissimilar metals separated by 3mm insulating washers

  • LCS enclosure in correct location as per ICF drawings and does not obstruct walkways - min 600mm clearance with doors open

  • LCS enclosure location does not obstruct maintenance access to other items of plant

  • There is no damage to the LSC enclosure

  • LCS enclosure shall be mounted not less than 1.2mt above the ground floor level and not more than 1.8 mt above the ground or floor level

  • Cable glands are correct type/ size and have been tightened

  • Shrouds have been fitted over glands and secured in place

  • Total number of terminal shall be 25% in excess of the number of incoming cable cores

  • All terminal number from 01 upwards

  • Wiring numbers clearly identified by ferrules

  • All cable terminations made using pre-insulated crimp lugs where appropriate

  • Electrical connections are tight

  • Stainless steel cable ID's fitted to cables

  • Hinged door earthed

  • No corrosion

  • All seals are satisfactory

  • LCS enclosure ID painted stainless steel fixed with 2 SS screws and clearly visible

  • No excessive movement

  • Spare cable entries sealed with plugs / IP rating maintained

  • Notes/Comments

APPROVALS

  • LCS Installation is

  • Actions to be taken:

  • Entered on Punch List

  • Punch list Reference Number:

  • Item No:

  • Person Completing the Checklist

  • Signature:

  • Agfab Approval By:

  • Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.